Section PSC 112.08 - Extensions of electric service under s. 196.495, Stats(1) In addition to any other conditions established by law or commission order, the measurement of an extension's length under s. 196.495(1) (b), Stats., shall be from an existing local service distribution line that is, or has been, actually used in rendering local service to a customer. A street light or security light is not a principal building or facility under s. 196.495(1) (b), Stats.(2) The commission shall enforce any written territorial agreement filed by 2 utilities, a utility and a cooperative association, or 2 cooperative associations to avoid duplication of facilities, if:(a) The agreement governs the extension of electric distribution lines and the right to serve customers; and(b) The commission has approved the agreement as being in the public interest.Wis. Admin. Code Public Service Commission PSC 112.08
CR Register, November, 1995, No. 479, eff. 12-1-95.