If a contractor makes a false certification with regards to § 457.8(a) or (b), or both (relating to certification of classification and capacity), the contractor shall pay to the Department as liquidated damages an amount equal to 5% of the total amount of the bid or the contractor may be disqualified from bidding on future work for 90 days, or both, as deemed appropriate. If the contractor fails to make the payment within 30 days of notification, the contractor shall be disqualified for 1 year. An application for renewal of prequalification will not be considered by the Department until the contractor makes payment. In lieu of the assessment of liquidated damages or disqualification, or both, the Secretary may issue a warning to the contractor making a false certification when the infraction is the first offense of the contractor.
67 Pa. Code § 457.9