An EU may choose to use an existing electric revenue meter if the following criteria are met:
1. The meter is capable of measuring the flow of electricity both into and out of the DGIC at the same time; and2. The meter is accurate to within plus or minus five percent when measuring excess energy flowing from the DGIC to the EU.