39 Miss. Code. R. 4-II-4-101

Current through December 10, 2024
Section 39-4-II-4-101

An EU may choose to use an existing electric revenue meter if the following criteria are met:

1. The meter is capable of measuring the flow of electricity both into and out of the DGIC at the same time; and
2. The meter is accurate to within plus or minus five percent when measuring excess energy flowing from the DGIC to the EU.

39 Miss. Code. R. 4-II-4-101

Adopted 1/3/2016
Amended 8/12/2022
Amended 11/6/2022