When a DGF is not approved under a Level 1 review, the Interconnection Customer may submit a new Interconnection Request for consideration under Level 2 or Level 3 procedures.
39 Miss. Code. R. 4-I-5-105
When a DGF is not approved under a Level 1 review, the Interconnection Customer may submit a new Interconnection Request for consideration under Level 2 or Level 3 procedures.
39 Miss. Code. R. 4-I-5-105