Within 10 business days of the estimated commissioning date indicated on the Interconnection Request, the EU shall, upon reasonable notice and at a mutually convenient time, conduct a Witness Test of the DGF to ensure that all equipment has been appropriately installed and that all electrical connections have been made in accordance with applicable codes.