39 Miss. Code. R. 4-I-5-100

Current through December 10, 2024
Section 39-4-I-5-100

The EU shall use Level 1 review procedures to evaluate Interconnection Requests when:

1. The DGF is inverter-based;
2. The DGF has a Nameplate Capacity of 20 kW or less; and
3. The Interconnection Equipment proposed for the DGF is Certified.

39 Miss. Code. R. 4-I-5-100

Adopted 1/3/2016
Amended 8/12/2022
Amended 11/6/2022