Section 5-41-6 - Channel changes; vegetative strips on new channels

On each new channel project, except a grassed waterway constructed for the purpose of conveying runoff without causing erosion or flooding, a vegetative strip shall be established and maintained for a width of 50 feet immediately adjoining the channel on each side of the stream if site conditions permit, unless an acceptable engineering design shows that a greater or lesser width of vegetative strip is preferable.

The general type of vegetation shall be approved by the chief engineer.

Kan. Admin. Regs. § 5-41-6

Authorized by K.S.A. 82a-303a; implementing K.S.A. 82a-303; effective May 1, 1987; amended Sept. 22, 2000.