Kan. Admin. Regs. § 5-41-5

Current through Register Vol. 43, No. 52, December 26, 2024
Section 5-41-5 - Channel changes; disposal of excavated material
(a) Material removed from the newly excavated channel shall be deposited at a location and in a form acceptable to the chief engineer. If the material is to be deposited so that it will have the effect of a levee, a separate prior written approval of the chief engineer is required pursuant to K.S.A. 24-126.
(b) Filling or plugging the original channel shall receive the prior written approval of the chief engineer.

Kan. Admin. Regs. § 5-41-5

Authorized by K.S.A. 82a-303a; implementing K.S.A. 82a-303; effective May 1, 1987.