* Authorization for coverage under reissuance or replacement of the general permit;
* The permittee's submittal of a notice of cessation;
* The issuance of an individual NPDES permit;
* A formal permit decision by the director not to reissue this general permit, at which time the permittee must seek coverage under an alternative general or individual permit; or
* A formal permit decision by the director to terminate the administrative extension due to the Permittee failing to submit by the deadline specified by the director, a complete NOI to request authorization to discharge under the new general permit.
The department shall notify the permittee in writing that its administrative extension is being terminated and the reason(s) why. An administrative extension of an NGPC granted, automatically or by notification, for a project which later is found to be in non-compliance may be terminated and may be required to apply for individual NPDES permit coverage.
The permittee who submits a notice of intent for renewal of the notice of general permit coverage shall be treated as an owner or operator applying for permit renewal under section 342D-6(h), HRS.
This paragraph does not apply to a notice of intent for small municipal separate storm sewer systems.
The person claiming automatic coverage on the notice of intent shall submit all site-specific plans, general contractor information, and all necessary permits and approvals (i.e., county-approved erosion and sediment control plan or approved substitute, approval to connect or discharge to a separate storm sewer system, etc.). Nothing in or with the notice of intent shall be submitted less than thirty days before the start of construction activities.
Haw. Code R. § 11-55-34.09