After certification of the LRDP for an educational facility has become final, the governing authority may undertake or authorize any development project for such educational facility within the coastal zone without a coastal development permit if:
If the Commission fails to act upon the notice of the impending development within thirty (30) days after the notice is filed in the office of the Commission, the development is deemed consistent with the certified LRDP.
Cal. Code Regs. Tit. 14, § 13548
Note: Authority cited: Section 30605, Public Resources Code. Reference: Sections 30605 and 30606, Public Resources Code.