Current through 2024 Act No. 225.
Section 58-33-287 - Review proceedings; consideration of settlement; discovery; contents and time for issuance of final order(A) The commission shall issue its order ruling upon a petition for review of a revised rates order within six months. If the petition for review has been resolved among the parties by settlement agreement, the commission shall consider and accept or reject any settlement agreement entered into by the parties within forty-five days. If a settlement agreement is reached between some but not all parties, then the settlement agreement, if approved by the commission, must be deemed to dispose of any issues resolved in it that have not been raised by other parties to the proceeding pursuant to Section 58-33-285(C).(B) Proceedings pursuant to Section 58-33-285 are limited to issues related to whether the revised rates filed by the utility comply with the terms of the commission order issued pursuant to Section 58-33-270 and with the specific requirements of Section 58-33-280. Matters determined in orders issued pursuant to the Utility Facility Siting and Environmental Protection Act, Section 58-27-810, and other applicable provisions or Section 58-33-270 are not subject to review in proceedings under this section.(C) In proceedings pursuant to Section 58-33-285, the commission shall allow limited discovery, and restrict the issues for discovery and hearing to whether the revised rates comply with the terms of the commission order issued pursuant to Section 58-33-270 and compliance with the specific requirements of Section 58-33-280.(D) The commission shall issue such motions to strike, protective orders, motions to quash, motions for costs and sanctions, and other rulings as are necessary to enforce the terms of this limitation.(E) The commission shall dismiss as a party any intervenor who, after notice, fails to abide by the limitations contained in this section.(F) The failure of the commission to enforce the terms of this section may be remedied by petition for writ of mandamus or supersedeas in the circuit court, which petition the court shall advance over all other matters on its docket and hear on an emergency basis, without the requirement of a formal answer or other return, such hearing to be held as soon as practicable upon twenty-four hours notice to the party against whom relief is sought. Proceedings related to the petitions may not serve to stay or delay proceedings before the commission.(G) The commission shall issue a final order that:(1) sets forth any changes that are required to the rates approved in the revised rates order;(2) determines the amount of any overcollection or undercollection of the revenues by the utility that resulted from application of the rates authorized in the revised rates order as compared to the rates authorized in the final order issued under this section; and(3) establishes a credit to refund the amount of an overcollection or a surcharge to collect the amount of an undercollection of revenues that arose during the time that the rates approved in the revised rates order, or imposed due to a failure of the commission to issue a revised rates order, were applicable and requires the utility to apply the credit or surcharge until such time as the overcollection or undercollection is exhausted.(H) If the final order increases the amount of capital costs for which the utility may recover its weighted average cost of capital through revised rates, the AFUDC booked on those capital costs between the issuance of the revised rates order and the final order shall remain on the books of the utility and shall not be reversed or adjusted. Surcharges related to undercollection of costs must be calculated without consideration of AFUDC amounts recognized on the capital costs during this period.(I) If the final order reduces the amount of capital cost for which the utility may recover its weighted average cost of capital through revised rates for reasons other than the conclusive finding that the capital costs were imprudently incurred, then the utility may resume accrual of AFUDC on any capital costs that were not included in rate recovery and may book an amount of AFUDC equal to the AFUDC not recognized during the time the rates approved in the revised rates order were in effect.2007 Act No. 16, Section 2, eff upon approval (became law without the Governor's signature on May 3, 2007).