Current through 2024 Act No. 225.
Section 58-33-285 - Review of revised rates order or failure to issue such order; Office of Regulatory Staff as party; intervention(A) Within thirty days of the issuance of a revised rates order pursuant to Section 58-33-280(E) of this article, or within thirty days of the failure by the commission to issue a revised rates order as required pursuant to Section 58-33-280(E), any aggrieved party may petition the commission for review of the revised rates order or of the failure to issue a revised rates order.(B) The Office of Regulatory Staff and the utility must be automatic parties to any proceedings under this section.(C) In filing for intervention under this section, intervenors shall identify with particularity the specific issues they intend to raise with regard to the revised rates order.(D) The party seeking review of the revised rates order shall serve a copy of such petition on the Office of Regulatory Staff and the utility on the same day and by the same means as it is provided to the commission.(E) Any filing under this section must be considered a new proceeding subject to the provisions of Section 58-33-240. The commission shall open a single new docket for all filings related to any one set of revised rates filed under this article.2007 Act No. 16, Section 2, eff upon approval (became law without the Governor's signature on May 3, 2007).