Current through October 11, 2024
Section 445A.417 - Major modification of existing permit1. A major modification to an existing permit requires a public notice.2. A major modification to an existing permit may extend the term of the permit for not more than 5 years.3. For the purposes of this section, "major modifications" include:(a) The addition of a new beneficiation process which includes, but is not limited to, heap leaching and process components for milling, which was not identified in the original application.(b) A significant change in the location of a proposed process component or site condition which was not adequately described in the original application.(c) A change in the proposed beneficiation process that significantly alters the characteristics of the waste stream which significantly increases the potential to degrade the waters of the State.Nev. Admin. Code § 445A.417
Added to NAC by Environmental Comm'n, eff. 9-1-89-Substituted in revision for NAC 445.24334NRS 445A.425, 445A.465, 445A.600