From Casetext: Smarter Legal Research

Miletta v. U.S.

United States District Court, D. New Jersey
May 27, 2005
Civil No. 02-1349 (JBS) (D.N.J. May. 27, 2005)

Summary

dismissing cross-claim pursuant to § 1367(c) because the court had expended "little if any judicial resources relating to the cross-claim," thus "there would be no significant duplication of effort if this claim were pursued elsewhere" and "resolution of this cross-claim would delay entry of final judgment on the underlying personal injury action"

Summary of this case from Korrow v. Aaron's Inc.

Opinion

Civil No. 02-1349 (JBS).

May 27, 2005

John R. Mininno, Esquire, MININNO LAW OFFICE, Collingswood, New Jersey, Counsel for Plaintiffs.

William A. Feldman, Esquire, FELDMAN FIORELLO, LLC, Wayne, Wayne, New Jersey, Counsel for Defendant Syska Hennessy, Inc. and Third-Party Defendant St. Paul Mercury Insurance Co.

John R. Gercke, Esquire, GERCKE, DUMSER, SHOEMAKER SIERZEGA, PC, Cherry Hill, New Jersey, Counsel for Defendant Ranco Construction, Inc.

James H. Landgraf, Esquire, CURETON CAPLAN, Delran, New Jersey, Counsel for Third-Party Plaintiff Ranco Construction, Inc.

Bruce A. Tritsch, Esquire, Fairfield, New Jersey, Counsel for Defendant Joseph Trongone, Jr., Inc.


OPINION


This matter arose when Plaintiff Steven Miletta fell roughly fifteen feet through a skylight on the roof of a building he had been subcontracted to repair. Following a nine day trial, a jury awarded compensatory damages in favor of Steven Miletta in the amount of $100,000, and awarded his wife, Plaintiff Kelly Miletta, $0. The following post-trial motions have been filed:

(1) plaintiffs' motion for a new trial [Docket Item 122];
(2) motion by Defendant Ranco for "Reconsideration of the Court's Opinion Issued on 10-6-03 . . . or, In the Alternative, Judgment on the Issue of Indemnification From Joseph Trongone, Inc. Pursuant to the Subcontract Between Ranco Construction Co., Inc. and Joseph Trongone, Inc." [Docket Item 120];
(3) motion for summary judgment by Defendant Trongone seeking dismissal of Ranco Construction's amended cross-claims [Docket Item 118];
(4) cross-motion by Defendant Syska Hennessy seeking an order compelling Defendant Ranco to pay 70% of Syska Hennessy's total reasonable defense costs and attorney's fees [Docket Item 124]; and
(5) "Application for Entry of Judgment On Defendant Ranco Construction, Inc.'s Affirmative Claim" (by James Landgraf, Esquire) [Docket Item 119.]

Magistrate Judge Joel B. Rosen, by Order dated August 15, 2003, granted the motion by Ranco Construction for leave to amend its cross-claim and required that Ranco Construction serve and file the amended pleadings no later than September 5, 2003. [Docket Item 57.] Ranco never filed an amended cross-claim, though Trongone has waived any objection to this procedural defect.

I. BACKGROUND

In June 1997, the United States and Syska Hennessy CEM ("Syska Hennessy") entered into contract number DACA 87-97-D-0039 for renovations to Building 5651, an existing housing facility at the Fort Dix, New Jersey, military base. Syska Hennessy subcontracted the project's roofing work to Ranco Construction ("Ranco"); Ranco subcontracted certain aspects of the roofing work to Joseph Trongone, Jr., Inc. ("Trongone"); and Trongone subcontracted the structural steel work to Miletta Brothers, Inc., a company for which Plaintiff Steven Miletta was acting as principal owner, officer, and project superintendent on April 5, 2001 — the date Steven Miletta fell through a skylight on the roof of Building #5651.

Plaintiff subsequently brought suit against the United States and the above private contractors seeking compensatory damages for past and future pain and suffering and loss of enjoyment. Plaintiff Kelly Miletta brought suit seeking compensatory damages for loss of services from her husband both following the accident and during recovery.

The Court instructed the Jury at the close of all evidence that "Plaintiff Steven Miletta does not seek, nor should your Verdict include, damages for past or future medical care or for past or future wage loss." [Docket Item 111.]

Plaintiffs originally brought this action against the United States pursuant to the Federal Tort Claims Act, 28 U.S.C. § 1346(b). By Opinion and Order dated July 21, 2004, the Court granted the motion for summary judgment by the United States, and dismissed all claims against it. [Docket Items 77, 78.] The Court retained supplemental jurisdiction over Plaintiffs' remaining state law claims under 28 U.S.C. § 1367(a).

Following a nine day trial, the Jury returned its verdict on March 24, 2005, in favor of Steven Miletta, finding Mr. Miletta 50% comparatively negligent, Defendant Syska Hennessy 30% negligent, Defendant Ranco 15% negligent, and Defendant Trongone 5% negligent. The Jury awarded compensatory damages in favor of Steven Miletta in the amount of $100,000, and awarded Plaintiff Kelly Miletta $0. The Court thereafter molded this verdict in accordance with the pretrial agreement of all parties to include in the judgment the worker's compensation lien of $175,685.21. The Court added prejudgment interest of $43,633.79 for a total gross award of $319,319.03. (Order for Final Judgment filed April 8, 2005.) Applying the jury's verdicts of Plaintiff's and Defendants' respective negligence to the gross award, the Court entered final judgment in favor of Plaintiff Steven Miletta in the amount of $95,795.71 against Syska Hennessy, $47,897.85 against Ranco Construction, and $15,965.95 against Joseph Trangone, Inc. (Id.)

II. DISCUSSION

A. Plaintiffs' Motion for a New Trial

Plaintiffs have timely moved for a new trial on all issues, arguing that the jury verdict was a compromise between damages and liability. If Plaintiffs are correct, the Court must order a new trial. Pryer v. C.O. 3 Slavic, 251 F.3d 448, 456-57 (3d Cir. 2001) (holding where damages award is the result of a compromise a new trial should be ordered as to all issues). If, on the other hand, the Court merely finds that the damages awarded to either Plaintiff is insufficient as a matter of law, it may, in its discretion, grant a partial new trial as to the issue of damages.

The Court does not have the option of ordering anadditur. Under New Jersey law, "the term additur is used to describe an order denying the plaintiff's application for a new trial on condition that the defendant consent to a specified increase in the jury's award." Fisch v. Manager, 130 A.2d 815, 818 (N.J. 1957). It is well-settled under New Jersey law "that the practice of . . . additur violate[s] none of our constitutional interdictions and, if fairly invoked, serve[s] the laudable purpose of avoiding a further trial where substantial justice may be attained on the basis of the original trial."Id. at 823. In the federal courts, however, additur is prohibited by the force of the provision in the Seventh Amendment guaranteeing the right to trial by jury and that "no fact tried by a jury shall be otherwise re-examined by any court of the United States, than according to the rules of the common law."Fisch, 130 A.2d at 818-19 (citing Dimick v. Schiedt, 293 U.S. 474 (1936) (approving the use of remittitur but prohibiting the practice of additur)). In fact, a federal court may never increase a judgment for a stated amount above that awarded by a jury, either directly or indirectly. 11 Wright, Miller Kane § 2816.

Because the Court does not agree that the Jury returned a compromise verdict or that the damages awarded were unreasonably low, however, the Court will not disturb the verdict reached by the Jury.

Plaintiffs additionally reiterate their objection at trial to the testimony of the defense expert, Michael Wright, as "an inadmissible net opinion." (Pls. Br. at 6.) By Oral Opinion delivered on March 22, 2005, the Court denied Plaintiffs'Daubert motion, and limited Wright's testimony further at various points in his testimony. Plaintiffs have offered no new arguments at this time and the Court will not revise its earlier rulings.

1. Rule 59(a) of the Federal Rules of Civil Procedure

Rule 59(a), Fed.R.Civ.P., provides:

A new trial may be granted to all or any of the parties and on all or part of the issues . . . in an action in which there has been a trial by jury, for any of the reasons for which new trials have heretofore been granted in actions at law in the courts of the United States. . . .

"Rule 59 gives the trial judge ample power to prevent what he considers to be a miscarriage of justice. It is the judge's right, and indeed, his duty, to order a new trial if he deems it in the interest of justice to do so." 11 Charles A. Wright, Arthur R. Miller Mary Kay Kane § 2803 (2d ed. 1995). In other words, a district court may, in its "exercise of discretion" "grant a new trial if required to prevent injustice or to correct a verdict that was against the weight of the evidence." The American Bearing Co. v. Litton Indus., Inc., 729 F.2d 943, 947 (3d Cir. 1984).

2. New Jersey Court Rule 4:49-1(a)

The standard of review under New Jersey law is substantially similar to the federal one. Under N.J. Court Rule 4:49-1(a):

A new trial may be granted to all or any of the parties and as to all or part of the issues on motion made to the trial judge. . . . The trial judge shall grant the motion if, having given due regard to the opportunity of the jury to pass upon the credibility of the witnesses, it clearly and convincingly appears that there was a miscarriage of justice under the law.

Where the motion is for a new trial on damages, the motion "should not be granted unless the damage verdict is so disproportionate to the injury and resulting disability as to shock the court's conscience and convince it that to sustain the award would be manifestly unjust, that is, unless it clearly and convincingly appears that there was a miscarriage of justice under the law." Tronolone v. Palmer, 539 A.2d 1224, 1226 (N.J.Super.Ct. App. Div. 1988) (internal citations omitted) (citing N.J. Court Rule 4:49-1(a)); see Mahoney v. Podolnick, 773 A.2d 1102, 1117 (N.J. 2001) (emphasizing that a jury verdict should remain undisturbed "unless it constitutes a manifest injustice that shocks the judicial conscience"). In making its determination, the court should view the evidence in the light most favorable to the non-moving party. Mahoney, 773 A.2d at 1117.

3. Application of State or Federal Standard

"Motions for a new trial . . ., long considered to be within the exclusive purview of federal jurisprudence, were pulled into the vortex of substantive/procedural dichotomy by the Supreme Court's decision in Gasperini v. Center for Humanities, Inc."Hayes v. Cha, 338 F. Supp. 2d 470, 491 (D.N.J. 2004) (Rosen, Mag. J.). In Gasperini, 518 U.S. 415, 422 (1996), the United States Supreme Court decided "an important question regarding the standard a federal court uses to measure the alleged excessiveness of a jury's verdict in an action for damages based on state law." The implications of that decision are significant here as far as determining whether the state or federal standard of review should govern Plaintiffs' motion. See Hayes v. Cha, 338 F. Supp. 2d 470, for a thorough analysis of the Gasperini decision.

In Gasperini, the Court examined the standard for a new trial under New York law, as codified by the New York State Legislature in 1986, which required "closer court review" than the common law "shock the conscience test" which had up to that time been employed by both state and federal courts in New York. Justice Ginsburg, writing for a majority of the Court, noted that the New York statute was substantive insofar as it provided standards for reviewing jury awards, as well as procedural in that it assigned the ultimate decision-making authority to appellate courts. The Court concluded that "New York's law controlling compensation awards for excessiveness or inadequacy can be given effect, without detriment to the Seventh Amendment, if the review standard set out in CPLR § 5501(c) is applied by the federal trial court judge, with appellate control of the trial court's ruling limited to review for `abuse of discretion.'" Id. at 419.

Here, unlike Gasperini, the state and federal standards of review for motions for a new trial are strikingly similar. See infra; Hayes, 338 F.Supp.2d at 487. "As the federal and New Jersey rules have similar intent, and the standards developed under these rules are virtually identical, this court shall apply the federal standard when reviewing the jury award, and not displace it with the state standard," Hayes, 338 F.Supp.2d at 487, looking to applications of the state standard only for guidance.

(a) The Jury Did Not Reach A Compromise Verdict

Plaintiffs seek a new trial on all issues, asserting that the jury verdict was inadequate as a matter of law as it was the result of a compromise on the questions of liability and damages. The Court is not persuaded that such is the case. In fact, the Jury's logical apportionment of liability among the three defendants demonstrates that its verdict was intelligent and reasonable. As the entire verdict has not been tainted so as to require a new trial as to all issues, the Court will limit its analysis to the issue of damages.

(b) Steven Miletta's $100,000 Recovery

The evidence at trial supports that Mr. Miletta suffered serious injuries resulting from his fall. For the twenty-six days following the accident, Mr. Miletta was confined to intensive care. At trial, Stuart Dubowitch, an expert in orthopedic medicine, testified that he twice saw Mr. Miletta as a patient and that he reviewed Mr. Miletta's extensive medical records. Dr. Dubowitch testified that Mr. Miletta suffered severe head lacerations, multiple broken ribs, a collapsed lung, a head injury, and a shoulder injury. Additionally, Dubowitch testified that Mr. Miletta was hypoxic, meaning that he was not getting enough oxygen. Dubowitch described to the Jury in detail how difficult it was for Mr. Miletta to breathe following the accident, causing Plaintiff to remain in critical condition for his first week in intensive care. Because of Mr. Miletta's difficulty with breathing, a tracheotomy tube was inserted into Plaintiff's neck where it remained for roughly 21 days. Also, Plaintiff needed catheterization to aid him in excreting waste.

Moreover, Joseph Miletta, Jr. testified that he saw Plaintiff Miletta immediately after the accident and that he appeared unconscious. Joseph Miletta testified that he visited Steven Miletta in the hospital every day and that for roughly the first three weeks Plaintiff was "completely out." Joseph Miletta testified to the medical equipment being utilized to support Plaintiff and that medical staff had inserted a long needle into Plaintiff's lungs to drain excess fluid. Mr. Miletta also testified in detail to the pain and suffering he endured following the accident and during his recovery.

Additionally, however, there was evidence that Mr. Miletta's recovery was successful once he was discharged from the hospital. For example, there was testimony that shortly after returning home from the hospital Mr. Miletta traveled a considerable distance from Cedarville to the site of his accident at Ft. Dix-McGuire Air Force Base. Moreover, the Jury saw how easily Mr. Miletta could get up from a kneeling position without having to exert significant pressure on his hand. Finally, the Jury heard testimony that Mr. Miletta was working full-time in his steel fabrication business (albeit with certain physical limitations) within eight months after the accident, and that he has not received medical care related to this accident in several years.

This demonstration was ostensibly an attempt by Miletta to disprove that immediately prior to the accident he pushed on the skylight cover to help him get up from the roof.

Based on the above, it was reasonable for the Jury to have concluded that Mr. Miletta was entitled to no more than $100,000. In Lombardo v. Hoag, 634 A.2d 550 (N.J.Super.Ct. App. Div. 1993), cert. denied, 640 A.2d 850 (N.J. 1994), the plaintiff was riding in the bed of a pickup truck that was involved in an accident. Plaintiff suffered severe injuries, including a fracture subluxation of the spine resulting in compression of his spinal cord, severe neck pain, leg spasms, vomiting, loss of sensation on his left side and inability to move his extremities. After undergoing surgery, the plaintiff continued to need catheterization and suppositories to aid him in excreting waste. Also, the plaintiff continued to suffer from spasticity.

The plaintiff made continued progress through treatment and therapy, however, and even though at the time of trial he suffered from a limp and was still complaining of pain and limited movement in his neck and arm, he had not received medical treatment beyond checkups in the 5 years preceding trial. The court in Lombardo upheld a $200,000 jury verdict, concluding that the jury could have reasonably relied on the "remarkable recovery" made by the plaintiff to justify its damages award.

This Court has determined that the Jury here could have similarly relied on a successful recovery theory in awarding Mr. Miletta no more than $100,000 for his past and future pain, suffering and loss of enjoyment. Following the close of evidence, the Court properly instructed the Jury: "If you find for Mr. Miletta, he is entitled to recover fair and reasonable money damages for the full extent of the harm caused, no more and no less." [Docket Item 111.] The Court is convinced that the Jury followed that instruction. Far from shocking this Court's conscience, the Court believes that the result reached by the Jury was fair.

Merely because the verdict may have been less than anticipated or hoped for by the plaintiff is no more reason to set aside the verdict and grant a new trial than a verdict that may be substantially higher than expected by a defendant. Under our system of jury trials, litigants inevitably run the risk that the jury's determination of the amount of damages may vary substantially from reasonable expectations of litigants.
Governali v. American Tempering, Inc., 1988 U.S. Dist. LEXIS 265, at *14 (E.D.Pa. Jan. 20, 1988). This Court will not upset the jury's verdict.

(c) Mrs. Miletta's $0 Recovery

Plaintiffs also seek a new trial on Mrs. Miletta's claim for loss of services and companionship. The question presented by this motion is much closer than that for her husband. However, for the reasons now explained, the Court will likewise not disturb the jury's verdict as to Mrs. Miletta.

Generally, "[o]ne who by reason of his tortious conduct is liable to one spouse for . . . bodily harm is subject to liability to the other spouse for the resulting loss of the society and services of the first spouse. . . ." Restatement (Second) Torts § 693 (1977). A narrower issue is before the Court here — namely, whether recovery by one spouse for tortious conduct of a third party requires an award of damages to the other spouse for loss of services and companionship. Other courts have had the occasion to answer this question and this Court will look to those decisions for guidance.

In Governali, supra, 1998 U.S. Dist. LEXIS 265, a husband and wife brought an action against a company, claiming that the negligence of one of the company's employees was a proximate cause of an accident involving Mr. Governali. Specifically, Mr. Governali was injured when he was struck by a 600 to 900 pound roll of plastic which fell from a forklift being operated by one of the defendant's employees. Following the liability phase of a bifurcated trial, the jury found that the defendant was 70% negligent and Mr. Governali was 30% negligent. After the damage phase of trial, the jury awarded Mr. Governali $150,000 for past and future medical expenses, past and future pain and suffering, and past and future loss of earning capacity. The jury returned a verdict of zero for his wife on her claim for loss of consortium. The plaintiffs filed a motion for a new trial as to both liability and damages arguing that the damage award for Mr. Governali was inadequate and that the $0 verdict for Mrs. Governali represented an "inconsistent verdict."

Under Pennsylvania law, loss of consortium includes loss of services. Hopkins v. Blanco, 302 A.2d 855 (Pa.Super.Ct. 1973), aff'd, 320 A.2d 139 (Pa. 1974).

In denying Mrs. Governali's motion for a new trial, the district court in Governali explained that "[w]hile Mrs. Governali did testify with regard to her loss of consortium, the jury was free to accept or reject her testimony even though it was uncontradicted and unrefuted." 1998 U.S. Dist. LEXIS 265, at *15. Moreover, the court held that "the verdict of zero is not logically inconsistent with the jury's award of $150,000.00 to Mr. Governali. It can logically be concluded that the jury found that Mrs. Governali's loss of consortium was not caused by the injuries sustained by Mr. Governali in the accident." Id.

In McPeek v. Lockhart, 2005 Tenn. App. LEXIS 199, at *8 (Tenn.Ct.App. March 24, 2005), the court noted that although a claim for loss of services is a derivative claim, it is separate from the injured spouse's claim. The court explained that

According to the court in McPeek, under Tennessee law a claim for loss of services is part of a claim for loss of consortium. For ease of exposition, this Court will substitute "loss of services" for "loss of consortium" in its discussion of the McPeek decision.

a jury verdict finding for the injured spouse but also denying a [loss of services] claim is not necessarily inconsistent because [loss of services] is "a distinct and separate cause of action from that of the injured spouse's claim." As [loss of services] is its own separate cause of action, it does not necessarily follow that simply because the injured spouse is found to have a legitimate claim that there then must be [loss of services] for the non-injured spouse.
Id. at *9.

There, Mr. and Mrs. McPeek sued the defendant following an automobile accident in which Mrs. McPeek was injured. Following a jury trial, Mrs. McPeek was found to be 40% at fault. The jury awarded Mrs. McPeek $4,000 and awarded her husband $0 on his claim for loss of services. The plaintiffs challenged that result, arguing on appeal that the verdict was inadequate because the jury failed to award loss of services to the husband. The court disagreed with the plaintiffs that the award of zero damages was unreasonable, summarizing the pertinent evidence as follows:

Plaintiffs testified that prior to the accident, Ms. McPeek did things for her husband including cooking meals and helping him get out of the bathtub. Although both plaintiffs claimed that things were not like they were prior to the accident, Mr. McPeek admitted that his wife still is able to cook meals and Ms. McPeek testified that she now cooks meals that are quick and easy rather than big meals. In addition, Ms. McPeek testified that instead of helping her husband to get out of the bathtub and to the bedroom to put on his prosthetic leg as she used to, she now brings the prosthetic leg to the bathroom for him.
Id. at *10. Moreover, Mr. McPeek testified that prior to his wife's accident "[s]he did everything for me." Id. at *2. The court held that despite the wife's diminished physical capacity and ability to provide certain services to her husband — most notably, helping him walk — the zero dollar award was reasonable.

In McPeek the plaintiffs offered more extensive testimony on the loss of services claim than Plaintiffs have here. Indeed, in McPeek both the husband and wife offered testimony on the loss of services claim. In this case, that Mr. Miletta did not testify on this issue at trial only further supports the conclusion that the jury's award should not be disturbed.

In Rangolan v. County of Nassau, 51 F.Supp.2d 236 (E.D.N.Y. 1999), aff'd in part, rev'd in part on other grounds, 370 F.3d 239 (2d Cir. 2004), the court held that damages for loss of services does not automatically follow to one spouse from a finding of liability on the other spouse's tort claims. In that case, the district court granted the defendant's motion for a new trial, thereby overturning a jury's verdict in favor of a husband and wife. The jury had awarded the husband $1,250,000 for injuries suffered when he was assaulted while in custody at the Nassau County Correctional Center. The wife was awarded $60,000 for her loss of services claim.

There, the husband was incarcerated at the time he was assaulted by a fellow inmate. As a result of the assault, the plaintiff lapsed into a coma for three days. The plaintiff's expert testified at trial that the plaintiff suffered a right sided depressed skull fracture with a small subarachnoid hemorrhage. Additionally, the expert testified that the plaintiff sustained a cerebral concussion with post concussion syndrome and headaches, a fractured skull, a circular scar on the side of the head, and organic brain damage diagnosed as post-traumatic seizure disorder.

The defense expert's prognosis was less severe.

On the issue of loss of services (which included loss of companionship and society) the plaintiff's wife testified that they lived together for one year prior to his incarceration. Following the accident, the husband was transferred to another correctional facility where he remained at the time of the trial. In addition, the court noted that there was no evidence offered concerning the services that the husband performed for the wife. During the husband's incarceration, his wife visited him six times.

In granting the defendant a new trial, the court in Rangolan relied primarily on the fact that the husband was incarcerated from the time of the accident forward. The court explained that "it is difficult for the Court to imagine, and the evidence has not revealed, how [the wife] has suffered loss of services while her husband has been in custody. . . ." Id. at 243-44. Furthermore, the court concluded that even if the two plaintiffs ultimately reunite following his release, "it is difficult to visualize what loss of services will result from [the husband's] residual damages, namely depression, headaches, and possible seizures." Id. at 244.

As noted in the discussion below, however, the court did acknowledge that companionship and society "can be reasonably inferred from the state of marriage itself." Rangolan, 51 F.Supp.2d at 244.

This Court believes that the reasoning explicated in the above decisions is sound and should be applied to the facts of this case. Accordingly, the Court holds that, under New Jersey law, Mrs. Miletta is not per se entitled to recovery for loss of services and companionship solely based on recovery by her husband for his negligence claims. Indeed, the Court instructed the Jury following the presentation of evidence that Mrs. Miletta is only "entitled to fair and reasonable compensation for any loss or impairment of her spouse's services because of his injuries, which has been sustained by her as a proximate result of the defendants' negligence." [Docket Item 111.] Nothing relieved Plaintiffs from their burden of proof as to such damages for loss of services and companionship.

Moreover, based on the evidence it would have been reasonable for the Jury to conclude that Mr. Miletta did not provide the services about which Mrs. Miletta testified. At trial, Mrs. Miletta testified that the Miletta's son, Joey, was born on June 2, 2000 and that "Steve helped with the baby in every way." (3/21/05 Trial Testimony.) According to Kelly Miletta, this included changing diapers as well as feeding and bathing the baby. (Id.) Additionally, Mrs. Miletta testified that before Mr. Miletta's accident, Mr. Miletta would take sole care of the baby every Tuesday night, which included midnight feedings. Mrs. Miletta testified that while Mr. Miletta was in intensive care, and for several months after his return home from the hospital, he was unable to assist with the care of the baby.

Notably, however, Mr. Miletta did not testify that he helped feed and bathe their son prior to his accident, or that he was unable to do so afterwards. To be sure, Defendants did not cross-examine Mrs. Miletta nor did they offer direct evidence contradicting her testimony. However, the Jury was free to give little or no weight to Mrs. Miletta's testimony. Accordingly, the jury's determination that Mrs. Miletta suffered no loss of services is reasonable.

By this conclusion the Court does not suggest that the testimony given by Mrs. Miletta was not truthful. Indeed, at oral argument counsel for Defendants were unable to point to any specific testimony which should have been construed by the Jury to be false. Rather, the Court is merely pointing out that a jury is free to make its own credibility determinations and give testimony the weight it believes is appropriate. That the Jury was unimpressed by Mrs. Miletta's claimed losses of her husband's assistance in caring for their infant is within the province of the jury.

Mrs. Miletta also testified that Mr. Miletta had begun construction on an addition to their home but that after his accident he was unable to work on the project. Because no evidence was offered that Mrs. Miletta paid someone else to finish the project while Mr. Miletta was recovering and because the project only remained in an unfinished state for a relatively short while, it was reasonable for the Jury to have awarded Mrs. Miletta nothing for her loss of services related thereto.

Similarly, the jury's zero award for Mrs. Miletta's loss of companionship claim does not shock the judicial conscience. To be sure, in Rangolan, supra, the court held that some loss of companionship "can be reasonably inferred from the state of marriage itself." 51 F.Supp.2d at 244. In that case, the jury had awarded the wife of the assault victim $60,000 on her loss of services claim. The defendant subsequently moved for a new trial, arguing that the jury award was unreasonably high, and the court ordered a remittitur in the amount of $20,000. The court there, however, determined the remittitur amount based on the maximum amount a reasonable jury could have awarded, where the original award was excessive. It does not logically follow from that conclusion that a zero dollar award in a different case, under different facts, would be unreasonable. Similarly here, that a positive award would have been reasonable does not require a holding that a $0 recovery is per se inadequate. In short, the evidence in this case, when weighed by the Jury, could reasonably support its conclusion, or a contrary conclusion awarding at least modest damages.

For the above reasons, the $0 award for Mrs. Miletta's loss of services and companionship claim will stand.

B. Motion for Reconsideration By Ranco

Once again this Court is being asked to interpret the indemnification clause contained in the subcontractor agreement between Syska Hennessy and Ranco, and to apply the jury's findings regarding the respective liability of Ranco (15%) and Syska Hennessy (30%). A party seeking reconsideration of a decision "must show more than a disagreement with the court's decision." Panna v. Firstrust Sav. Bank, 760 F. Supp. 432, 435 (D.N.J. 1991); see L.Civ.R. 7(I). Instead, the party seeking reconsideration must show either that (1) there was an intervening change in the controlling law; (2) new evidence became available that was not available when the court issued its decision; or (3) reconsideration is needed to correct a clear error of law or fact or to prevent manifest injustice. Max's Seafood Café v. Quinteros, 176 F.3d 669, 677 (3d Cir. 1999). By its present motion, Ranco is able to satisfy this last requirement and, thus, its motion for reconsideration will be granted.

This matter originally came before the Court upon the motion of Syska Hennessy for partial summary judgment seeking a declaration that it is entitled, under its subcontractor agreement with Ranco, to full indemnification and reimbursement from Ranco so long as Syska Hennessy is not wholly liable for Plaintiffs' injuries. [Docket Item 46]. The Court denied that motion [Docket Items 63, 64] and Ranco filed a motion for reconsideration [Docket Item 66] which the Court denied. [Docket Item 72]. Ranco has now filed a second motion for reconsideration [Docket Item 120] and Syska Hennessy has filed a cross-motion for summary judgment seeking an order compelling Defendant Ranco to pay "70% of [Syska Hennessy's] total reasonable defense costs and attorney's fees in connection with the defense of above-entitled litigation." [Docket Item 124.]

Syska Hennessy erroneously argues in opposition that the motion by Ranco is untimely under Rule 59(e), Fed.R.Civ.P., and that the requirements of Rule 60(b), Fed.R.Civ.P., have not been met. The instant motion, however, is governed by L.Civ.R. 7(I), the requirements of which have been satisfied, as explained below.

The indemnification clause in the contract between Syska Hennessy and Ranco provides:

4.6.1. To the fullest extent permitted by law, the Subcontractor [Ranco Construction] shall indemnify and hold harmless the Owner, Contractor [Syska Hennessy], Contractor's consultants, and agents and employees of any of them from and against claims, damages, losses and expenses, including but not limited to attorney's fees, arising out of or resulting from performance of the Subcontractor's Work under this Subcontract, provided that any such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), but only to the extent caused by the negligent acts or omissions of the Subcontractor [Ranco Construction], the Subcontractor's Sub-subcontractors [Joseph Trongone, Jr., Inc. and Miletta Brothers], anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder [Syska Hennessy]. Such obligation shall not be construed to negate, abridge, or otherwise reduce other rights or obligations of indemnity which would otherwise exist as to a party or person described in this Paragraph 4.6.

By Opinion and Order dated October 6, 2003, this Court denied in part the motion for partial summary judgment by Syska Hennessy, holding in the first instance:

The indemnification clause, when read in its totality, clearly provides that Ranco Construction is only required to indemnify to the extent of its, or its subcontractor's, fault. It is required to do so if Syska Hennessy is not at fault; it is required to do so even if Syska Hennessy is partially at fault. Its obligation remains the same; it must indemnify, but only to the extent that the damages were incurred by its, or its subcontractor's, negligence. With this reading, the "regardless" clause is not surplusage, but instead ensures contractually that the common law rule of indemnification is not followed, namely that "a party seeking common law indemnification from another must be without fault." See Huck v. Gabriel Realty, 136 N.J. Super. 468, 474 (Law Div. 1975) (citing Public Service Electric Gas Co. v. Waldroup, 38 N.J. 419, 432 (1956) for common law rule). Thus, here, the "regardless" clause makes clear that Syska Hennessy may seek indemnification even if it is not without fault, but does not change its clear proviso that Syska Hennessy may only seek indemnification to the extent that the damages are caused by Ranco Construction or its subcontractors.

(10/6/03 Slip. Op. at 9-10.) As to the issue of defense costs, however, the Court agreed with Syska Hennessy that "the clause requires Ranco Construction to indemnify it for its fees in an amount equal to the percentage of fault of Ranco Construction and its subcontractors." (Id. at 10.) The Court reasoned that

[i]n this case, where joint liability is likely so that there will likely be no one but-for cause of the accident, the accident likely would not have occurred, and Syska Hennessy would not have incurred any defense costs, if others, including Ranco Construction and its subcontractors, were not involved. In other words, because if it is found that Syska Hennessy did not cause this accident on its own, it would follow that Syska Hennessy would not have had to defend a lawsuit at all if it were the only contractor involved. Thus, in the event that joint liability is proven involving Ranco Construction and its subcontractors, Syska Hennessy will have incurred fees that it would not have incurred but for the negligence of the other joint tortfeasors, which would include Ranco Construction and its subcontractors. Under the terms of the indemnification clause, Syska Hennessy is entitled to indemnification for such amounts incurred because of the fault of Ranco Construction and its subcontractors.

(Id. at 11.) Ranco subsequently asked the Court to reexamine its holding, which the Court did. By Memorandum Order dated February 13, 2004, the Court again explained that "Syska Hennessy [would] bear the percentage of its attorneys fees that is equal to its percentage of fault for the accident." [Docket Item 72.]

Following the jury trial, and pursuant to the Court's April 11, 2005 Scheduling Order, Ranco again moves for reconsideration. Ranco maintains that absent any imputed liability to Syska Hennessy due to the negligence of Ranco or its subcontractors, Ranco is not required to indemnify Syska Hennessy for any of its attorney's fees or costs. (Ranco Br. at 3.) In light of the theory of negligence of these Defendants presented to the Jury (which did not seek to make Syska Hennessy liable on a theory of respondeat superior for the negligence of Ranco or others), and the jury's findings as to the apportionment of negligence among the parties, this Court agrees.

The indemnification agreement between Syska Hennessy and Ranco provides that Ranco will indemnify Syska Hennessy for all expenses, including but not limited to attorney's fees, to the extent caused by Ranco, Trongone or Miletta, "regardless of whether or not such expense is caused in part by" Syska Hennessy. (emphasis added). The Jury in this case, however, returned a verdict that Syska Hennessy was itself 30% liable for Mr. Miletta's injuries. In other words, the Jury found that none of Syska Hennessy's 30% liability was "arising out of or resulting from" the subcontractors' work but, rather, arose only from Syska Hennessy. Accordingly, the legal costs incurred by Syska Hennessy were caused entirely (not "in part") by its independent negligence and not that of any of the other defendants. Syska Hennessy had to defend itself entirely because of its own negligence, and not due to the negligence of Ranco, even in part. Therefore, Ranco is not obligated to indemnify Syska Hennessy for those costs.

To be sure, Syska Hennessy argues that it's negligence was "passive" and that the jury's apportionment of liability to Syska Hennessy was "based on the asserted non-delegability of site safety responsibility as general contractor." (SH Opp. Br. at 8.) While the contractor has overall responsibility for site safety under New Jersey law, and the Jury was so instructed, the Court did not instruct the Jury on respondeat superior liability nor did any party argue that theory of liability to the Jury. The Jury found each defendant's separate liability, as well as the comparative negligence of Mr. Miletta. At no time was the Jury instructed that another party's negligence could be attributed to Syska Hennessy. Thus, the Court is confident that the 30% liability ascribed to Syska Hennessy is solely due to Syska Hennessy's own acts and omissions, and not Ranco's, even in part.

In case any doubt remains, the New Jersey Supreme Court has made clear that "[t]he right to legal costs follows the right to indemnification." Mantilla v. NC Mall Assocs., 770 A.2d 1144, 1151 (N.J. 2001). Mantilla involved a personal injury claim arising from a slip and fall at Newport Mall in Jersey City, New Jersey ("Mall"). The plaintiff sued the Mall as well as the company hired by the Mall to perform cleaning services ("PBS"). At the conclusion of the trial, the jury awarded the plaintiff $197,000 in damages and apportioned the negligence in the following way: 40% to the Mall; 50% to PBS; and 10% to the plaintiff. Following entry of judgment, the Mall moved pursuant to an indemnity agreement with PBS to compel PBS to pay for its litigation expenses and to provide indemnification for its part of the judgment.

The court in Mantilla held "that absent explicit contractual language to the contrary, an indemnitee who has been found to be at least partially at fault may not recover the costs of its defense from an indemnitor." 770 A.2d at 1145. Moreover, because the court there determined that the relevant agreement between the Mall and the defendant cleaning service did not include such language, the agreement did not "override contractually" the "default rule" that "an indemnitee who has defended against allegations of its independent fault may not recover its [defense] costs." Id. at 1150 (alteration in original) (citations omitted). The court in Mantilla further held that because there was

clearly evidence of the Mall's independent negligence . . ., we hold that Newport Mall's defense costs were losses resulting from its own negligence and not that of PBS. The right to legal costs follows the right to indemnification. Because the PBS-Newport contract failed to express in unequivocal terms that PBS would indemnify Newport Mall for legal expenses incurred in defending itself against claims of it own negligence, we conclude that PBS cannot be held responsible for those costs. That result follows because the PBS-Newport Mall contract does not expressly state that PBS will indemnify Newport Mall for the costs of defending against claims of Newport Mall's negligence.
Id. at 1151. Several years later, the New Jersey Supreme Court reaffirmed Mantilla, holding that "in order to allay even the slightest doubt on the issue of what is required to bring a negligent indemnitee within an indemnification agreement, we reiterate that the agreement must specifically reference the negligence or fault of the indemnitee." Azurak v. Corporate Property Investors, 814 A.2d 600, 601 (N.J. 2003).

As in Mantilla, the agreement between Syska Hennessy and Ranco does not explicitly provide that Ranco will indemnify Syska Hennessy for the costs of defending its independent negligence. This Court previously recognized as much when it held that Ranco "is only required under the agreement to indemnify to the extent of its, or its subcontractor's, fault." (Slip op. at 9.) The Court's holding on that question is dispositive as to the issue of indemnification for legal costs as well. As Mantilla made clear, in cases such as this, where the indemnitee is not entitled to indemnification for damages caused by its own negligence, certainly it can not recover defense costs resulting therefrom.

For the above reasons, the motion by Defendant Ranco for reconsideration will be granted, and judgment upon Syska Hennessy's cross-claim for indemnification will be entered in favor of Ranco, and the cross-motion by Syska Hennessy will be denied.

Counsel for Defendant Ranco, John Gercke, agreed at oral argument on May 5, 2005 to abandon its cross-claim for contractual indemnification against Defendant Trongone in the event that Ranco's motion for reconsideration was successful. Regardless, as the relevant language contained in the indemnification agreement between Ranco and Trongone is substantially similar to that contained in the agreement between Syska Hennessy and Ranco, the analysis above applies with full force to Ranco's cross-claim for contractual indemnification. For these reasons, summary judgment will also be entered in favor of Trongone on Ranco's cross-claim for contractual indemnification.

C. Application by Ranco For Entry of Judgment

Ranco has additionally moved, through its counsel James Landgraf, Esq., for entry of judgment in its favor and against Syska Hennessy and its payment bond surety, third-party defendant St. Paul Mercury Insurance Co. ("St. Paul"), jointly and severally, pursuant to 40 U.S.C. § 3133. The amount of the judgment sought is $73,139.00, together with interest calculated pursuant to 31 U.S.C. § 3901 et seq.

St. Paul is not a party to the underlying personal injury action. It is named in Ranco's third-party complaint only as the surety of Syska Hennessy upon the payment bond.

Syska Hennessy has stipulated that the unpaid balance being withheld on its subcontract with Ranco is $77,139.00. (Joint Pre-Trial Order, Part II ¶ 17.) Syska Hennessy has withheld payment of that sum, however, arguing for the first time, post-trial, that Ranco, its insurance carrier (Ohio Casualty), and Ranco's attorney, Mr. Gercke, intentionally and wrongfully withheld that Syska Hennessy had been certified as an additional insured under the Ranco policy issued by Ohio Casualty. Ohio Casualty is not represented in this case, nor has Syska Hennessy filed such a claim against Ohio Casualty. Such a suit remains a future possibility. Because Syska Hennessy's payment obligations to Ranco are separate and distinct from any obligation Ranco may have had to inform Syska Hennessy of its status as an additional insured, the Court will grant Ranco's motion and enter judgment against Syska Hennessy and St. Paul and in favor of Ranco for the following reasons.

The Court has jurisdiction over this claim pursuant to 28 U.S.C. § 1331 and 40 U.S.C. § 3133(b).

Pursuant to 40 U.S.C. § 3133:

Every person that has furnished labor or material in carrying out work provided for in a contract for which a payment bond is furnished under section 3131 of this title and which has not been payed in full within 90 days after the day on which the person did or performed the last of the labor or furnished or supplied the material for which the claim is made may bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought and may prosecute the action to final execution and judgment for the amount due.

The Miller Act, 40 U.S.C. § 3131 et seq., was codified at 40 U.S.C. § 270a et seq. prior to the 2002 revision.

"The Miller Act requires a general contractor on a federal project to post a surety bond to protect those who supply labor and materials for the project, and enables suppliers to bring suit on the bond for any unpaid amounts, whether owed by the general contractor or one of its subcontractors." United States ex rel. Casa Redmix Concrete Corp. v. Luvin Construction Corp., 2001 U.S. Dist. LEXIS 6184, at *4 (S.D.N.Y. May 11, 2001) (granting plaintiff's motion for summary judgment on Miller Act claim).

Four elements must be proven to collect under this section: (1) that labor and materials were furnished pursuant to the particular contract at issue; (2) that the supplier of the labor and materials is unpaid; (3) that the supplier had a good faith belief that the labor and materials were intended for the specified work; and (4) the plaintiff gave written notice to defendants within 90 days of the date of the last labor furnished or materials supplied. Id.

Here, there is no dispute that all four elements have been satisfied. First, Syska Hennessy concedes that Ranco furnished labor and materials specified under the subcontractor agreement; second, there remains an unpaid balance of $73,139.00 for the labor performed and materials supplied; finally, Ranco provided notice and demand for payment upon Syska Hennessy by letter dated January 23, 2003, less than 90 days after it submitted its final invoice. Accordingly, judgment will be entered in favor of Ranco in the amount of $77,139.00.

Additionally, Ranco seeks interest on the unpaid balance. The Prompt Payment Act, 31 U.S.C. § 3905, provides: "Each construction contract awarded by an agency shall include a clause that requires the prime contractor to include in each subcontract for property or services entered into by the prime contractor and a subcontractor (including a material supplier) for the purpose of performing such construction contract" both a "payment clause" and an "interest penalty clause." The former requires the prime contractor to pay the subcontractor for "satisfactory performance" within seven days. The latter obligates the prime contractor to pay the subcontractor an "interest penalty" on amounts due in the case of each payment not properly made.

The relevant language of the subcontractor agreement between Syska Hennessy and Ranco states:

The Subcontractor shall be entitled to be paid an interest penalty of any late payment computed at the rate of interest established by the Secretary of Treasury and published in the Federal Register, for interest payments under Section 12 of the Contract Disputes Act of 1978 in effect at the time the Contractor accrues the obligation to pay an interest penalty as specified in the Prompt Payment Act.

(Agreement ¶ 4.7.1, Ranco Ex. D.)

Under the Prompt Payment Act, "the interest penalty shall be paid for the period beginning on the day after the required payment date and ending on the date on which payment is made." 31 U.S.C. § 3902(b). The interest shall be computed at the rate of interest established by 41 U.S.C. § 611. The rate to be applied to interest paid pursuant to that provision is the variable rate established at 6 month intervals rather than the fixed rate in effect at the time the interest begins to run.

Here, Ranco is seeking interest on the unpaid balance commencing February 8, 2003 through the present. (Ranco Br. at 4.) The following interest rates apply to the relevant periods:

This date represents ninety days from Ranco's presentation of its November 8, 2002 application to Syska Hennessy.

1/1/2003 — 6/30/2003 4.250% 7/1/2003 — 12/31/2003 3.125% 1/1/2004 — 6/30/2004 4.000% 7/1/2004 — 12/31/2004 4.500% 1/1/2005 — 6/30/2005 4.250%

(Ranco Ex. E.) Because simple, not compound, interest is awarded under 41 U.S.C. § 611, a per diem calculation may be utilized:

2/8/2003 — 6/30/2003 $8.52 per diem (142 days) 7/1/2003 — 12/31/2003 $6.26 per diem (184 days) 1/1/2004 — 6/30/2004 $8.01 per diem (181 days) 7/1/2004 — 12/31/2004 $9.02 per diem (184 days) 1/1/2005 — 5/26/2005 $8.52 per diem (146 days)

Based on these figures, Ranco is entitled to interest on the unpaid balance of $73,139.00 in the amount of $6,715.09 through May 26, 2005. A $79,854.09 judgment will be entered in favor of Ranco and against Syska Hennessy and St. Paul, jointly and severally.

The Court declines Syska Hennessy's counsel's request to delay entry of judgment upon this undisputed Miller Act claim for Ranco's work completed and not paid for, pending some future assertion and resolution of Syska Hennessy's potential claim that Ranco and Ohio Casualty failed to advise it of its alleged other-insured status under Ohio Casualty's policy. The Court declines to exercise its discretion in favor of such a stay in light of the Miller Act's policy for prompt payment of subcontractors on federally funded construction projects, see 31 U.S.C. § 3902, supra, as well as the uncertain viability of this potential, unasserted claim. That Syska Hennessy recently discovered an alleged notice of such other-insured status in itsown files does not strengthen its hand, but this Court — and indeed the parties themselves — lack sufficient information, let alone evidence, upon this subject, and no determination can be made.

D. This Court Will Decline to Exercise Supplemental Jurisdiction Over the Remaining Non-Diverse State Law Claim by Ranco Against Trongone for Breach of Contract

The remaining claim before the Court is a cross-claim by Ranco against Trongone for breach of contract, namely, Ranco's claim that Trongone had promised to add Ranco as an "other insured" under Trongone's insurance policy but failed to do so. The Court will decline to exercise supplemental jurisdiction over this claim pursuant to 28 U.S.C. § 1367(c) and it will be dismissed without prejudice.

Section 1367(a) provides that "in any civil action of which the district courts have original jurisdiction, the district courts shall have supplemental jurisdiction over all other claims that are so related to claims in the action within such original jurisdiction that they form part of the same case or controversy under Article III of the United States Constitution." 28 U.S.C. § 1367(a). Subsection (c) of § 1367 enumerates the four categories of claims over which a district court has supplemental jurisdiction but which the court may decline to adjudicate:

(c) The district courts may decline to exercise supplemental jurisdiction over a claim under subsection (a) if —
(1) the claim raises a novel or complex issue of State law,
(2) the claim substantially predominates over the claim or claims over which the district court has original jurisdiction,
(3) the district court has dismissed all claims over which it has original jurisdiction, or
(4) in exceptional circumstances, there are other compelling reasons for declining jurisdiction.
28 U.S.C. § 1367(c). "Section 1367(c) . . . was intended simply to codify the preexisting pendent jurisdiction law, enunciated inGibbs and its progeny, concerning those instances in which a district court is authorized to hear a state claim it would have the power to hear because of its relationship to an original federal jurisdiction claim." Borough of West Mifflin v. Lancaster, 45 F.3d 780, 788 (3d Cir. 1995); see United Mine Workers of America v. Gibbs, 383 U.S. 715 (1966). "The statute . . . reflects the understanding that, when deciding whether to exercise supplemental jurisdiction, `a federal court should consider and weigh in each case, and at every stage of the litigation, the values of judicial economy, convenience, fairness, and comity.'" City of Chicago v. Int'l College of Surgeons, 522 U.S. 156, 173 (1997) (quoting Carnegie-Mellon University v. Cohill, 484 U.S. 343, 350 (1988)).

Of particular importance here is the second category of claims described in section 1367(c)(2) — those which "substantially predominate" over the federal claims. As the Third Circuit has instructed, the language of that provision is adapted directly from Gibbs and, thus, it "should be understood in that context." West Mifflin, 45 F.3d at 788. The Court held inGibbs that "if it appears that the state issues substantially predominate, whether in terms of proof, of the scope of the issues raised, or of the comprehensiveness of the remedy sought, the state claims may be dismissed without prejudice and left for resolution to state tribunals." 383 U.S. at 726-27. The Third Circuit has cautioned, however, that

[i]t is important to recognize that this standard [under 1367(c)(2)] was fashioned as a limited exception to the operation of the doctrine of pendent jurisdiction — a doctrine that seeks to promote judicial economy, convenience, and fairness to litigants by litigating in one case all claims that arise out of the same nucleus of operative fact. When a district court exercises its discretion not to hear state claims under § 1367(c)(2), the advantages of a single suit are lost. For that reason, § 1367(c)(2)'s authority should be invoked only where there is an important countervailing interest to be served by relegating state claims to state court.
West Mifflin, 45 F.3d at 789.

In the present case, whether Trongone was to provide insurance coverage to Ranco, and the consequences, if any, of Trongone's failure to do so, do not arise from the same facts and circumstances as the original federal claim of Plaintiffs against the United States. When the Court dismissed the Federal Tort Claims Act case against the United States, it retained supplemental jurisdiction over Plaintiffs' personal injury claims against the defendant contractors, and the contractors' crossclaims among themselves relating to the liability for Plaintiffs' claims, as these were so related to the original federal jurisdiction claim under the FTCA that "they form[ed] part of the same case or controversy under Article III," within the meaning of 28 U.S.C. § 1367(a), supra. See Bank of India v. Trendi Sportswear, 239 F.3d 428, 436-37 (2d Cir. 2000) ("It is well-settled that a third-party action for indemnification comes within a court's ancillary jurisdiction."). Those claims and indemnification-related cross-claims were tried to a verdict and also adjudicated herein.

This remaining claim by Ranco against Trongone for insurance coverage, however, depends upon entirely different facts surrounding the alleged making of a contract between those parties and the understandings of those parties regarding that obligation. This dispute does not fall within the exceptional circumstances for exercising supplemental jurisdiction outlined in § 1367(c), supra, and the Court declines to retain such jurisdiction over this remaining claim.

Even if the Court could retain jurisdiction over this crossclaim, because judicial economy, convenience and fairness to the litigants would not be served by doing so, the Court would dismiss the claim under § 1367(c)(2). In the first instance, the parties have not undertaken substantial discovery on this claim. Likewise, this Court has expended little if any judicial resources relating to the cross-claim. In other words, the burden of this non-diverse state claim would be the same for a state tribunal as it would for this Court — there would be no significant duplication of effort if this claim were pursued elsewhere. Finally, resolution of this cross-claim would delay entry of final judgment on the underlying personal injury action.

Indeed, Ranco itself maintains that its own cross-claim "should be dismissed without prejudice on jurisdictional grounds." (Ranco Opp. at 3.) Nor was Trongone advocating this Court's retention of supplemental jurisdiction in this aspect of the case.

For these reasons, the remaining cross-claim by Ranco for breach of contract will be dismissed without prejudice pursuant to 28 U.S.C. § 1367(c)(2).

III. CONCLUSION

For the reasons expressed in this Opinion, the Court will deny Plaintiffs' motion for a new trial [Docket Item 122]; grant Ranco's motion for reconsideration; grant the motion by Trongone for summary judgment on Ranco's cross-claim for contractual indemnification [Docket Item 118]; deny the motion by Syska Hennessy seeking payment by Ranco of 70% of its reasonable attorney's fees and costs [Docket Item 124] and enter judgment upon Syska Hennessy's cross-claim for indemnification [Docket Item 15] in favor of Ranco; dismiss without prejudice the cross-claim by Ranco against Trongone for breach of contract [Docket Item 23]; and grant Ranco's application for judgment [Docket Item 119] in the amount of $79,854.09 against Syska Hennessy and its payment bond surety, third-party defendant St. Paul Mercury Insurance Co.

The accompanying Order is entered.


Summaries of

Miletta v. U.S.

United States District Court, D. New Jersey
May 27, 2005
Civil No. 02-1349 (JBS) (D.N.J. May. 27, 2005)

dismissing cross-claim pursuant to § 1367(c) because the court had expended "little if any judicial resources relating to the cross-claim," thus "there would be no significant duplication of effort if this claim were pursued elsewhere" and "resolution of this cross-claim would delay entry of final judgment on the underlying personal injury action"

Summary of this case from Korrow v. Aaron's Inc.
Case details for

Miletta v. U.S.

Case Details

Full title:STEVEN MILETTA and KELLY MILETTA, Plaintiffs, v. UNITED STATES OF AMERICA…

Court:United States District Court, D. New Jersey

Date published: May 27, 2005

Citations

Civil No. 02-1349 (JBS) (D.N.J. May. 27, 2005)

Citing Cases

W. Sur. Co. v. Hudson Ins. Co.

Additionally, a contractor must demonstrate that labor and materials were furnished pursuant to the…

Schildknecht v. Twp. of Montclair

ecapitulation of the cases and arguments considered by the court before rendering its original decision'"…