Section 38-8A-25 - Preventive treatment-Grounds for performance by conservation district board

The board may perform the treatment ordered pursuant to § 38-8A-24 if the person named in the order fails to commence treatment within three days from the date of mailing, posting, or serving of notice, or at a later time specified by the order. The board may also perform the treatment if:

(1) The treatment is not performed in the manner and to the extent specified;
(2) Prior to the expiration date fixed in the order, the person named in the order advises the board he cannot or does not intend to accomplish the work.