Any party aggrieved by the issuance of a certificate of site compatibility or electric transmission facility construction permit from the commission, certification of continuing suitability filed by a utility with the commission, or promulgation of a final order by the commission, may request a rehearing by the commission. The hearing must be conducted pursuant to chapter 28-32. There is a right of appeal to the district court from any adverse ruling by the commission.
N.D.C.C. § 49-22-19