Payment must be made monthly to the contractor for all work done or material furnished, in such amount as must be determined by the director, but in no event less than ninety percent nor more than ninety-nine percent thereof, and payment must be made in full upon the completion of the contract and acceptance of the work.
N.D.C.C. § 24-02-25