When an application is filed, the auditor, by order, shall set the time and location for a hearing on the application. Ten days before the hearing, notice of the hearing must be published in each affected county and notice by mail given to the engineer, the attorney for the petitioners, and the auditor of each affected county. The contractor must pay the cost of publishing the hearing notice.
The drainage authority may, by order, reduce the contractor's bond if it determines that the contractor is not in default and that a loss will not result from reducing the bond. The bond may be reduced to an amount sufficient to protect the affected counties from loss and damage, but the reduction:
Minn. Stat. § 103E.545
1990 c 391 art 5 s 74