After receiving the petition, the county auditor must verify the signatures and notify the county board. Within 30 days after being notified of the petition, the county board must hold a public hearing on whether the requested lake improvement district should be established.
Within 30 days after holding the public hearing, the county board shall, by order, establish or deny the establishment of the petitioned lake improvement district. An order establishing a district must conform to section 103B.535 and may modify the petition relating to the district's boundaries, functions, financing, or organization.