Mich. Comp. Laws § 324.4909

Current through Public Act 156 of the 2024 Legislative Session
Section 324.4909 - Priority establishment and project certification procedures; compliance prerequisite to grant

Notwithstanding any other provision of this part or of any rule of the department, compliance with sections 4909 to 4912 is a prerequisite to the making of a grant under this part. Sections 4909 to 4912 provide procedures for establishing the priority of eligible projects and for certifying projects for grants for construction of collecting sewers.

MCL 324.4909

1994, Act 451, Eff. 3/30/1995 .