Current through P.L. 171-2024
Section 5-30-4-2 - Conflict of interest(a) A member of the technical review committee may not:(1) submit a proposal for; or(2) furnish design services or construction services under; the design-build contract.
(b) The design-builder may not delegate or subcontract professional services or construction services under the design-build contract to a member of the technical review committee.(c) Each member of the technical review committee must certify for each request for proposals that there is not a conflict of interest between the member and the design-builder responding to the request for proposals. If a conflict of interest exists, the member must be replaced before the review of any proposal.As added by P.L. 74-2005, SEC.1.