Current through P.L. 171-2024
Section 13-21-6-7 - Criteria for consideration in evaluation of proposals The board:
(1) shall evaluate proposals received under this chapter with regard to net cost or net revenues; and(2) in the manner consistent with provisions set forth in the requests for proposals, may evaluate proposals on the basis of additional factors such as the following: (A) The technical evaluation of facility design.(B) Net energy efficiency.(C) Environmental protection.(D) Overall system reliability.(E) Financial condition of the proposer.Pre-1996 Recodification Citation: 13-9.5-8-3(5).
As added by P.L. 1-1996, SEC.11.