Within thirty-five (35) days from the date of final completion of the work of improvement, the retention withheld by the owner shall be released, except in the event of a dispute between the owner and the original contractor, the owner may withhold from the final retention payment an amount not to exceed one hundred fifty percent (150%) of the estimated value of the issue in dispute. The owner may condition the final release of the retention upon receipt of satisfactory lien waivers from all persons with actual or potential lien claims on the work of improvement.