Before providing net metering service under this section, a Class II or III net metering facility shall provide all necessary information to, and cooperate with, the distribution utility to which it is interconnected to enable the distribution utility to obtain the appropriate asset identification for reporting generation to ISO -NE.
The department may only approve a proposal for a monthly minimum reliability contribution after the aggregate nameplate capacity of installed solar generating facilities in the commonwealth is equal to or greater than 1,600 megawatts. The department shall conduct a full adjudicatory proceeding when reviewing proposals for a monthly minimum reliability contribution, which shall include at least 1 public hearing and an opportunity for public comment.
The department may exempt or modify any monthly minimum reliability contribution for low-income ratepayers. The department may also exempt, for any period through the year 2020, any class or sub-class of Class I, Class II, or Class III net metering facilities that were in service not later than December 31, 2016 from any minimum reliability contribution. Minimum monthly reliability contributions shall take effect on such date designated by the department. The department may approve changes to the monthly minimum reliability contributions for individual electric distribution companies in any future base distribution rate proceeding, consistent with this section.
Mass. Gen. Laws ch. 164, § 139