Track 1: The remedial program shall achieve a cleanup level that will allow the site to be used for any purpose without restriction and without reliance on the long-term employment of institutional or engineering controls, and shall achieve contaminant-specific remedial action objectives for soil which conform with those contained in the generic table of contaminant-specific remedial action objectives for unrestricted use developed pursuant to subdivision six of this section. Provided, however, that volunteers whose proposed remedial program for the remediation of groundwater may require the long-term employment of institutional or engineering controls after the bulk reduction of groundwater contamination to asymptotic levels has been achieved but whose program would otherwise conform with the requirements necessary to qualify for Track 1, shall qualify for Track 1.
Track 2: The remedial program may include restrictions on the use of the site or reliance on the long-term employment of engineering and/or institutional controls, but shall achieve contaminant-specific remedial action objectives for soil which conform with those contained in one of the generic tables developed pursuant to subdivision six of this section without the use of institutional or engineering controls to reach such objectives.
Track 3: The remedial program shall achieve contaminant-specific remedial action objectives for soil which conform with the criteria used to develop the generic tables for such objectives developed pursuant to subdivision six of this section but may use site specific data to determine such objectives.
Track 4: The remedial program shall achieve a cleanup level that will be protective for the site's current, intended or reasonably anticipated residential, commercial, or industrial use with restrictions and with reliance on the long-term employment of institutional or engineering controls to achieve such level. The regulations shall include a provision requiring that a cleanup level which poses a risk in exceedance of an excess cancer risk of one in one million for carcinogenic end points and a hazard index of one for non-cancer end points for a specific contaminant at a specific site may be approved by the department without requiring the use of institutional or engineering controls to eliminate exposure only upon a site specific finding by the commissioner, in consultation with the commissioner of health, that such level shall be protective of public health and environment. Such finding shall be included in the draft remedial work plan for the site and fully described in the notice and fact sheet provided for such work plan.
N.Y. Envtl. Conserv. Law § 27-1415