S.C. Code § 58-27-2600

Current through 2024 Act No. 225.
Section 58-27-2600 - Definitions

As used in this article:

(A) "Customer-generator lessee" means the lessee of a renewable electric generation facility which:
(1) generates electricity from a renewable energy resource;
(2) has an electrical generating system with a capacity of:
(a) not more than the lesser of one thousand kilowatts (1,000 kW AC) or one hundred percent of contract demand if a nonresidential customer; or
(b) not more than twenty kilowatts (20 kW AC) if a residential customer;
(3) is located on a premises or residence owned, operated, leased, or otherwise controlled by the customer-generator lessee that is also the premises or residence served by the renewable electric generation facility;
(4) is interconnected and operates in parallel phase and synchronization with the retail electric provider for the premises or residence and has been approved by that retail electric provider;
(5) is intended only to offset part or all of the customer-generator lessee's own retail electrical energy requirements for each respective premises or residence or to enable the customer-generator lessee to obtain a credit for or engage in the sale of energy from the renewable electric generation facility to that customer-generator lessee's retail electric provider or its designee; and
(6) meets all applicable safety, performance, interconnection, and reliability standards established by the commission or the retail electric provider, the National Electrical Code, the National Electrical Safety Code, the Institute of Electrical and Electronics Engineers, Underwriters Laboratories, the federal Energy Regulatory Commission, and any local governing authorities.
(B) "Retail electric provider" means an electrical utility as defined in Section 58-27-10 and also means other entities that provide retail electric service in South Carolina, but excluding electric cooperatives organized under the laws of a state other than South Carolina.

S.C. Code § 58-27-2600

Added by 2014 S.C. Acts, Act No. 236 (SB 1189), s 4, eff. 6/2/2014.

2014 Act No. 236, Sections 9, 10, provide as follows:

"SECTION 9. If the application of the provisions of this act to any wholesale electrical contract existing on the date of its adoption is determined to impair unlawfully any term of such contract or to add material costs to either party, then that contract will be exempt from the terms of this act to the extent necessary to cure such impairment or to avoid the imposition of additional material costs.

"SECTION 10. Article 23, Chapter 27, Title 58 shall be construed as a whole, and all parts of it are to be read and construed together. If any part of this article shall be adjudged by any court of competent jurisdiction to be invalid, the remainder of this article shall be invalidated. Nothing herein shall be construed to affect the parties' right to appeal the matter."