Iowa Code § 327G.65

Current through March 29, 2024
Section 327G.65 - Cost of construction

The railroad corporation may require the person primarily to be served to pay the legitimate cost and expense of acquiring, by condemnation or purchase, the necessary right-of-way for the spur track and of constructing it, as determined in separate items by the department. Except as provided in section 327G.66, the total cost as ascertained by the department shall be deposited with the railroad corporation before it is required to incur expense. If an agreement cannot be reached, the question shall be referred to the department which may, after a hearing conducted by the department of inspections, appeals, and licensing, issue an order.

Iowa Code § 327G.65

89 Acts, ch 273, §39; 2023 Acts, ch 19, § 2007

Amended by 2023 Iowa, ch 19, s 2007, eff. 7/1/2023.
C24, 27, 31, 35, 39, §8172; C46, 50, 54, 58, 62, 66, 71, 73, 75, §481.4; C77, 79, 81, §327G.65; 81 Acts, ch 22, §2289 Acts, ch 273, §39

Referred to in §327G.68