Cal. Pub. Resources Code § 21100.2

Current through the 2024 Legislative Session.
Section 21100.2 - Time limits
(a)
(1) For projects described in subdivision (c) of Section 21065, each state agency shall establish, by resolution or order, time limits that do not exceed the following:
(A) One year for completing and certifying environmental impact reports.
(B) One hundred eighty days for completing and adopting negative declarations.
(2) The time limits specified in paragraph (1) shall apply only to those circumstances in which the state agency is the lead agency for a project. These resolutions or orders may establish different time limits for different types or classes of projects, but all limits shall be measured from the date on which an application requesting approval of the project is received and accepted as complete by the state agency.
(3) No application for a project may be deemed incomplete for lack of a waiver of time periods prescribed in state regulations.
(4) The resolutions or orders required by this section may provide for a reasonable extension of the time period in the event that compelling circumstances justify additional time and the project applicant consents thereto.
(b) If a draft environmental impact report, environmental impact report, or focused environmental impact report is prepared under a contract to a state agency, the contract shall be executed within 45 days from the date on which the state agency sends a notice of preparation pursuant to Section 21080.4. The state agency may take longer to execute the contract if the project applicant and the state agency mutually agree to an extension of the time limit provided by this subdivision.
(c) This section shall become operative January 1, 2018.

Ca. Pub. Res. Code § 21100.2

Added by Stats 2012 ch 487 (AB 2564),s 5, eff. 9/23/2012.