Section 25-9 - Building Sewer Pipes

All building sewers shall be installed in accordance with the 2012 International Plumbing Code (IPC). In the absence of a locally approved plumbing code, and in addition to the IPC, the building sewer shall comply with the following:

(a) Suitable building sewer pipe materials are polyvinyl chloride (PVC) or acrylonitrile-butadiene-styrene (ABS). The septic tank inlet and outlet pipes shall be schedule 40 PVC or ABS pipe and shall span the excavations for the septic tank and/or dosing chamber. American Society for Testing and Materials (ASTM) D-3034 Standard Dimension Ratio (SDR) 35 plastic pipe may be used if the void at the tank's side is filled with material that is granular, clean, and compacted.

(b) Building sewer pipes shall be sized to handle the peak hourly flow from the building and shall not be smaller than four (4) inches in diameter. When two different sizes or types of sewer pipes are to be connected, a proper type of fitting or conversion adapter shall be used.

(c) Sewer pipe shall not decrease in size flowing downstream.

(d) Building sewer pipes shall be laid at a standard slope of 1/4 inch per foot, and shall not be flatter than 1/8 inch per foot.

(e) Cleanouts shall be provided between the structure and the tank, at branch connections, every change in alignment, and at least every 100 feet in straight runs.

(f) All sewer piping shall be laid on a firm bed throughout its entire length. It shall be protected from damage due to rocks, hard lumps of soil, debris, and the like.

(g) Special care shall be used to prevent lateral movement or deformation during backfill. The backfill material shall be compacted to a density at least equivalent to the trench walls. Backfill over the pipe shall be of sufficient depth to protect the pipe from expected traffic loads and the wastewater from freezing.