020-25 Wyo. Code R. § 25-2

Current through April 27, 2019
Section 25-2 - Objective

This Chapter contains the minimum standards for the design and construction of small wastewater systems that are defined by W.S. 35-11-103(c)(ix). In addition, this Chapter contains the minimum standards for the design and construction of Underground Injection Control (UIC) Class V facilities 5C1-5C3, 5C6, 5D1, 5E1, 5E3-5E5 as defined in Chapter 27, Appendices C and D.

The following situations will require the application package to be sealed, signed, and dated by a professional engineer (PE): non-domestic wastewater from commercial and industrial facilities, high strength wastewater, individual permits to construct, or standard soil absorption systems with a soil percolation rate that is either less than 5 minutes per inch (mpi) or more than 60 minutes per inch (mpi).

These standards pertain to permits required pursuant to Chapters 3 and 25, Wyoming Water Quality Rules and Regulations. The installation of all components of a small wastewater system require a permit to construct. Permits to construct are specified throughout this chapter as general permits, described in Chapter 3, Section 7; permit by rule, described in Chapter 3, Section 8; or as individual permits to construct, described in Chapter 3, Section 6.

020-25 Wyo. Code R. § 25-2

Amended, Eff. 7/27/2016.

Amended, Eff. 6/29/2018.