Current through November 25, 2024
Section PSC 112.01 - Application of rules(1) This chapter applies to proposed construction by any electric public utility, as defined in s. 196.01, Stats. Note: Additional requirements relating to certificates for proposed large or bulk electric generating facilities of 12,000 kW or more nominal capacity, or a high-voltage transmission line with associated facilities exceeding one mile in length designed for operation at 100 kV or more, are included in ss. PSC 111.41 to 111.43.
(2) Section PSC 112.08 applies to electric public utilities as defined in s. 196.01(5), Stats., and to electric cooperative associations.Wis. Admin. Code Public Service Commission PSC 112.01
CR Register, November, 1995, No. 479, eff. 12-1-95; correction in (2) made under s. 13.93(2m) (b) 7, Stats., Register April 2007 No. 616.