Wash. Admin. Code § 51-11C-408045

Current through Register Vol. 25-01, January 1, 2025
Section 51-11C-408045 - Section C408.5-Other systems commissioning

C408.5 Systems installed to meet Section C406 or C407.

Equipment, components, controls or configuration settings for systems which are included in the project to comply with Section C406 or C407 shall be included in the commissioning process required by Section C408.1.

C408.5.1 System testing. Functional performance testing for these appliances, equipment, components, controls and/or configuration settings shall demonstrate operation, function and maintenance serviceability for each of the commissioned systems in accordance with the approved construction documents.

Wash. Admin. Code § 51-11C-408045

Adopted by WSR 16-03-072, Filed 1/19/2016, effective 7/1/2016
Amended by WSR 19-24-040, Filed 11/26/2019, effective 7/1/2020