This section applies to permanent powered platform installations dedicated to interior or exterior building maintenance of a specific structure or group of structures under the scope of chapter 296-870 WAC, Powered platforms.
Note: | The building owner needs to base the certification on: 1. The field test of the installation done before it is first placed into service or following any major modification to an existing installation; and 2. All other relevant available information including, but not limited to: a. Test data; b. Equipment specifications; c. Verification by a registered professional engineer. |
Additional requirements for powered platforms can be found in chapter 296-870 WAC, Powered platforms.
Wash. Admin. Code § 296-880-30020