Wash. Admin. Code § 296-24-29413

Current through Register Vol. 24-21, November 1, 2024
Section 296-24-29413 - Chains and cables
(1) You must discard any three foot length of chain if at any time it is found to have stretched 1/3rd the length of a link.
(2) You must not place bolts or nails between two links to shorten chains.
(3) You must not splice broken chains by inserting a bolt between two links with the heads of the bolt and the nut sustaining the load, or pass one link through another and insert a bolt or nail to hold it.
(4) You must ensure that annealing of chains is done in properly equipped annealing furnaces and under the direct supervision of a competent person thoroughly versed in heat treating wherever annealing of chains is attempted.
(5) You must periodically inspect cables. You must file a copy of the report of the inspections of each running cable in a place readily accessible to the department, or authorized representative.

Click Here To View Image

CRANE SIGNALS

1.

You must not remove the load or the crane unless you understand the floor signal clearly.

2.

You must be careful that the load does not swing to injure your hook-on man/woman or other floorpersons; make certain they are in the clear.

3.

When raising or lowering the load, youmust see that it will safely clear adjacent stockpiles or machinery.

4.

You must never pick up a load greater than the capacity of your crane. In case of doubt, call your foreperson.

5.

Youmustnever do ANYTHING that is not safe.

6.

You must cooperate with your hook-on or floorperson. You and he/she are a team handling a valuable piece of equipment-Never let it become a hazard.

Wash. Admin. Code § 296-24-29413

Amended by WSR 15-24-100, Filed 12/1/2015, effective 1/5/2016

Statutory Authority: RCW 49.17.040, 49.17.050, 49.17.240, chapters 43.22 and 42.30 RCW. 80-17-015 (Order 80-21), § 296-24-29413, filed 11/13/80; Order 73-5, § 296-24-29413, filed 5/9/73 and Order 73-4, § 296-24-29413, filed 5/7/73.