9 Va. Admin. Code § 25-220-175

Current through Register Vol. 41, No. 9, December 16, 2024
Section 9VAC25-220-175 - Criteria for requesting and granting a public hearing in a permit action
A. During the public comment period on a permit action in those instances where a public hearing is not mandatory under state or federal law or regulation, interested persons may request a public hearing to contest the action or terms and conditions of the permit.
B. Requests for a public hearing shall contain the following information:
1. The name and postal mailing or email address of the requester;
2. The names and addresses of all persons for whom the requester is acting as a representative;
3. The reason for the request for a public hearing;
4. A brief, informal statement setting forth the factual nature and extent of the interest of the requester or the persons for whom the requester is acting as representative in the application or tentative determination, including an explanation of how and to what extent such interest would be directly and adversely affected by the issuance, denial, modification, or revocation of the permit in question; and
5. Where possible, specific references to the terms and conditions of the permit in question, together with suggested revisions and alterations to those terms and conditions that the requester considers are needed to conform the permit to the intent and provisions of the basic laws of the State Water Control Board.
C. Upon completion of the public comment period on a permit action, the director shall review all timely requests for public hearing filed during the comment period on the permit action and, within 30 calendar days following the expiration of the time period for the submission of requests, shall grant a public hearing, unless the permittee or applicant agrees to a later date if the director finds the following:
1. That there is a significant public interest in the issuance, denial, modification, or revocation of the permit in question as evidenced by receipt of a minimum of 25 individual requests for a public hearing;
2. That the requesters raise substantial, disputed issues relevant to the issuance, denial, modification, or revocation of the permit in question; and
3. That the action requested by the interested party is not on its face inconsistent with or in violation of the basic laws of the State Water Control Board for a water permit action, a federal law, or any regulation promulgated thereunder.
D. The director of DEQ shall notify by email or postal mail at his last known address (i) each requester and (ii) the applicant or permittee of the decision to grant or deny a public hearing.
E. If the request for a public hearing is granted, the director shall:
1. Schedule the hearing at a time between 45 and 75 days after emailing or mailing of the notice of the decision to grant the public hearing.
2. Cause or require the applicant to publish notice of a public hearing to be published once, in a newspaper of general circulation in the city or county where the facility or operation that is the subject of the permit or permit application is located, at least 30 days before the hearing date.
F. The public comment period shall remain open for 15 days after the close of the public hearing if required by § 62.1-44.15:01 of the Code of Virginia.
G. The director may, at the director's discretion, convene a public hearing in a permit action.

9 Va. Admin. Code § 25-220-175

Derived from Virginia Register Volume 39, Issue 5, eff. 11/23/2022.