H. Supplemental review. If a supplemental review is offered to the IC and the IC agrees to the supplemental review, the utility shall, within 10 business days of the request, provide to the IC an appropriate supplemental review agreement. To maintain its position in the utility's interconnection queue, the IC must execute the supplemental review agreement and return it to the utility, along with a deposit for the estimated cost of the supplemental review, within 15 business days after receipt of the agreement. If the IC fails to return the executed supplemental review agreement along with the deposit within 15 business days after receipt, the interconnection request shall be deemed withdrawn, and the IC shall lose its place in the utility's interconnection queue. The IC shall be responsible for the utility's actual costs of conducting the supplemental review. The IC shall pay any review costs that exceed the deposit within 30 business days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the utility shall return such excess within 30 business days of the invoice without interest.
Within 30 business days following receipt of the supplemental review agreement and deposit, the utility will determine if the SGF can be interconnected safely and reliably.
1. If so, and if the supplemental review reveals that no modifications are required to the IC's interconnection facilities, or to the system, or to an affected system, the utility shall forward an executable SGIA to the IC within 10 business days after the determination.2. If so, and modifications are required to the IC's interconnection facilities to allow the SGF to be interconnected consistent with safety, reliability, and power quality standards in this chapter, the utility shall forward an executable SGIA to the IC within 10 business days after confirmation that the IC has agreed to make the necessary changes at the IC's cost.3. If so, and minor modifications to the utility system are required to allow the SGF to be interconnected consistent with safety, reliability, and power quality standards in this chapter, the utility shall, within 10 business days after the determination, forward an executable SGIA to the IC that requires the IC to pay the costs of such system modifications prior to interconnection.4. If not, the interconnection request will be elevated to the Level 3 interconnection process. Interconnection may occur when, as may be required under the applicable subdivision 1, 2, or 3 of this subsection, the SGIA is fully executed and returned to the utility, the IC has made required payments to the utility, and required modifications are complete. If subdivision 4 of this subsection is applicable, interconnection shall occur in accordance with the Level 3 interconnection process.