Utah Admin. Code 645-301-800

Current through Bulletin No. 2024-21, November 1, 2024
Section R645-301-800 - Bonding and Insurance

The rules in R645-301-800 set forth the minimum requirements for filing and maintaining bonds and insurance for coal mining and reclamation operations under the State Program.

810. Bonding Definitions and Division Responsibilities.
811. Terms used in R645-301-800 may be found defined in R645-100-200.
812. Division Responsibilities -- Bonding.
812.100. The Division will prescribe and furnish forms for filing performance bonds.
812.200. The Division will prescribe by regulation terms and conditions for performance bonds and insurance.
812.300. The Division will determine the amount of the bond for each area to be bonded, in accordance with R645-301-830. The Division will also adjust the amount as acreage in the permit area is revised, or when other relevant conditions change according to the requirements of R645-301-830.400.
812.400. The Division may accept a self-bond if the permittee meets the requirements of R645-301-860.300 and any additional requirements in the State or Federal program.
812.500. The Division will release liability under a bond or bonds in accordance with R645-301-880 through R645-301-880.800.
812.600. If the conditions specified in R645-301-880.900 occur, the Division will take appropriate action to cause all or part of a bond to be forfeited in accordance with procedures of that Section.
812.700. The Division will require in the permit that adequate bond coverage be in effect at all times. Except as provided in R645-301-840.520, operating without a bond is a violation of a condition upon which the permit is issued.
820. Requirement to File a Bond.
820.100. After a permit application under R645-301 has been approved, but before a permit is issued, the applicant will file with the Division, on a form prescribed and furnished by the Division, a bond or bonds for performance made payable to the Division and conditioned upon the faithful performance of all the requirements of the State Program, the permit and the reclamation plan.
820.110. Areas to be covered by the Performance Bond are:
820.111. The bond or bonds will cover the entire permit area, or an identified increment of land within the permit area upon which the operator will initiate and conduct coal mining and reclamation operations during the initial term of the permit.
820.112. As coal mining and reclamation operations on succeeding increments are initiated and conducted within the permit area, the permittee will file with the Division an additional bond or bonds to cover such increments in accordance with R645-830.400.
820.113. The operator will identify the initial and successive areas or increments for bonding on the permit application map submitted for approval as provided in the application, and will specify the bond amount to be provided for each area or increment.
820.114. Independent increments will be of sufficient size and configuration to provide for efficient reclamation operations should reclamation by the Division become necessary pursuant to R645-301-880.900.
820.120. An operator will not disturb any surface areas, succeeding increments, or extend any underground shafts, tunnels, or operations prior to acceptance by the Division of the required performance bond.
820.130. The applicant will file, with the approval of the Division, a bond or bonds under one of the following schemes to cover the bond amounts for the permit area as determined in accordance with R645-301-830:
820.131. A performance bond or bonds for the entire permit area;
820.132. A cumulative bond schedule and the performance bond required for full reclamation of the initial area to be disturbed; or
820.133. An incremental-bond schedule and the performance bond required for the first increment in the schedule.
820.200. Form of the Performance Bond.
820.210. The Division will prescribe the form of the performance bond.
820.220. The Division may allow for:
820.221. A surety bond;
820.222. A collateral bond;
820.223. A self-bond; or
820.224. A combination of any of these bonding methods.
820.300. Period of Liability.
820.310. Performance bond liability will be for the duration of the coal mining and reclamation operations and for a period which is coincident with the operator's period of extended responsibility for successful revegetation provided in R645-301-356 or until achievement of the reclamation requirements of the State Program and permit, whichever is later.
820.320. With the approval of the Division, a bond may be posted and approved to guarantee specific phases of reclamation within the permit area provided the sum of phase bonds posted equals or exceeds the total amount required under R645-301-830 and 830.400. The scope of work to be guaranteed and the liability assumed under each phase bond will be specified in detail.
820.330. Isolated and clearly defined portions of the permit area requiring extended liability may be separated from the original area and bonded separately with the approval of the Division. Such areas will be limited in extent and not constitute a scattered, intermittent, or checkerboard pattern of failure. Access to the separated areas for remedial work may be included in the area under extended liability if deemed necessary by the Division.
820.340. If the Division approves a long-term, intensive agricultural postmining land-use, in accordance with R645-301-413, the applicable five- or ten-year period of liability will commence at the date of initial planting for such long-term agricultural use.
820.350. General.
820.351. The bond liability of the permittee will include only those actions which he or she is obligated to take under the permit, including completion of the reclamation plan, so that the land will be capable of supporting the postmining land use approved under R645-301-413.
820.352. Implementation of an alternative postmining land-use approved under R645-301-413.300 which is beyond the control of the permittee need not be covered by the bond. Bond liability for prime farmland will be as specified in R645-301-880.320.
830. Determination of Bond Amount.
830.100. The amount of the bond required for each bonded area will:
830.110. Be determined by the Division;
830.120. Depend upon the requirements of the approved permit and reclamation plan;
830.130. Reflect the probable difficulty of reclamation, giving consideration to such factors as topography, geology, hydrology and revegetation potential; and
830.140. Be based on, but not limited to, the detailed estimated cost, with supporting calculations for the estimates, submitted by the permit applicant.
830.200. The amount of the bond will be sufficient to assure the completion of the reclamation plan if the work has to be performed by the Division in the event of forfeiture, and in no case will the total bond initially posted for the entire area under one permit be less than $10,000.
830.300. An additional inflation factor will be added to the subtotal for the permit term. This inflation factor will be based upon an acceptable Costs Index.
830.400. Adjustment of Amount.
830.410. The amount of the bond or deposit required and the terms of the acceptance of the applicant's bond will be adjusted by the Division from time to time as the area requiring bond coverage is increased or decreased or where the cost of future reclamation changes. The Division may specify periodic times or set a schedule for reevaluating and adjusting the bond amount to fulfill this requirement.
830.420. The Division will:
830.421. Notify the permittee, the surety, and any person with a property interest in collateral who has requested notification under R645-301-860.260 of any proposed adjustment to the bond amount; and
830.422. Provide the permittee an opportunity for an informal conference on the adjustment.
830.430. A permittee may request reduction of the amount of the performance bond upon submission of evidence to the Division providing that the permittee's method of operation or other circumstances reduces the estimated cost for the Division to reclaim the bonded area. Bond adjustments which involve undisturbed land or revision of the cost estimate of reclamation are not considered bond release subject to procedures of R645-301-880.100 through R645-301-880.800.
830.440. In the event that an approved permit is revised in accordance with the R645 rules, the Division will review the bond for adequacy and, if necessary, will require adjustment of the bond to conform to the permit as revised.
830.500. An operator's financial responsibility under R645-301-525.230 for repairing material damage resulting from subsidence may be satisfied by the liability insurance policy required under R645-301-890.
840. General Terms and Conditions of the Bond.
840.100. The performance bond will be in an amount determined by the Division as provided in R645-301-830.
840.200. The performance bond will be payable to the Division.
840.300. The performance bond will be conditioned upon faithful performance of all the requirements of the State Program and the approved permit, including completion of the reclamation plan.
840.400. The duration of the bond will be for the time period provided in R645-301-820.300.
840.500. General.
840.510. The bond will provide a mechanism for a bank or surety company to give prompt notice to the Division and the permittee of any action filed alleging the insolvency or bankruptcy of the surety company, the bank, or the permittee, or alleging any violations which would result in suspension or revocation of the surety or bank charter or license to do business.
840.520. Upon the incapacity of a bank or surety company by reason of bankruptcy, insolvency, or suspension or revocation of a charter or license, the permittee will be deemed to be without bond coverage and will promptly notify the Division. The Division, upon notification received through procedures of R645-301-840.510 or from the permittee, will, in writing, notify the operator who is without bond coverage and specify a reasonable period, not to exceed 90 days, to replace bond coverage. If an adequate bond is not posted by the end of the period allowed, the operator will cease coal extraction and will comply with the provisions of R645-301-541.100 through R645-301-541.400 as applicable and will immediately begin to conduct reclamation operations in accordance with the reclamation plan. Mining operations will not resume until the Division has determined that an acceptable bond has been posted.
850. Bonding Requirements for UNDERGROUND COAL MINING AND RECLAMATION ACTIVITIES and Associated Long- Term Coal-Related Surface Facilities and Structures.
850.100. Responsibilities. The Division will require bond coverage, in an amount determined under R645-301-830, for long-term surface facilities and structures, and for areas disturbed by surface impacts incident to UNDERGROUND COAL MINING AND RECLAMATION ACTIVITIES, for which a permit is required. Specific reclamation techniques required for underground mines and long-term facilities will be considered in determining the amount of bond to complete the reclamation.
850.200. Long-term period of liability.
850.210. The period of liability for every bond covering long-term surface disturbances will commence with the issuance of a permit, except that to the extent that such disturbances will occur on a succeeding increment to be bonded, such liability will commence upon the posting of the bond for that increment before the initial surface disturbance of that increment. The liability period will extend until all reclamation, restoration, and abatement work under the permit has been completed and the bond is released under the provisions of R645-301-880.100 through R645-301-880.800 or until the bond has been replaced or extended in accordance with R645-301-850.230.
850.220. Long-term surface disturbances will include long-term coal-related surface facilities and structures, and surface impacts incident to underground coal mining activities which disturb an area for a period that exceeds five years. Long-term surface disturbances include, but are not limited to: surface features of shafts and slope facilities; coal refuse areas; powerlines; boreholes; ventilation shafts; preparation plants; machine shops, roads and loading and treatment facilities.
850.230. To achieve continuous bond coverage for long-term surface disturbances, the bond will be conditioned upon extension, replacement or payment in full, 30 days prior to the expiration of the bond term.
850.240. Continuous bond coverage will apply throughout the period of extended responsibility for successful revegetation and until the provisions of R645-301-880.100 through R645-301-880.800 inclusive have been met.
850.300. Bond Forfeiture. The Division will take action to forfeit a bond pursuant to R645-301-850 if 30 days prior to bond expiration the operator has not filed:
850.310. The performance bond for a new term as required for continuous coverage; or
850.320. A performance bond providing coverage for the period of liability, including the period of extended responsibility for successful revegetation.
860. Forms of Bonds.
860.100. Surety Bonds.
860.110. A surety bond will be executed by the operator and a corporate surety licensed to do business in Utah that is listed in "A.M. Best's Key Rating Guide" at a rating of A- or better or a Financial Performance Rating (FPR) of 8 or better, according to the "A.M. Best's Guide". All surety companies also will be continuously listed in the current issue of the U.S. Department of the Treasury Circular 570.
860.111. Operators who do not have a surety bond with a company that meets the standards of subsection 860.110. will have 120 days from the date of Division notification after enactment of the changes to subsection 860.110. in which to achieve compliance, or face enforcement action.
860.112. When the Division in the course of examining surety bonds notifies an operator that a surety company guaranteeing its performance does not meet the standard of subsection 860.110., the operator has 120 days after notice by mail from the Division to correct the deficiency, or face enforcement action.
860.120. Surety bonds will be noncancellable during their terms, except that surety bond coverage for lands not disturbed may be canceled with the prior consent of the Division. The Division will advise the surety, within 30 days after receipt of a notice to cancel bond, whether the bond may be canceled on an undisturbed area.
860.200. Collateral Bonds.
860.210. Collateral bonds, except for letters of credit, cash accounts and real property, will be subject to the following conditions:
860.211. The Division will keep custody of collateral deposited by the applicant until authorized for release or replacement as provided in R645-301-870 and R645-301-880;
860.212. The Division will value collateral at its current market value, not at face value;
860.213. The Division will require that certificates of deposit be made payable to or assigned to the Division both in writing and upon the records of the bank issuing the certificates. If assigned, the Division will require the banks issuing these certificates to waive all rights of setoff or liens against those certificates;
860.214. The Division will not accept an individual certificate of deposit in an amount in excess of $100,000 or the maximum insurable amount as determined by the Federal Deposit Insurance Corporation or the Federal Savings and Loan Insurance Corporation.
860.220. Letters of credit will be subject to the following conditions:
860.221. The letter may be issued only by a bank organized or authorized to do business in the United States;
860.222. Letters of credit will be irrevocable during their terms. A letter of credit used as security in areas requiring continuous bond coverage will be forfeited and will be collected by the Division if not replaced by other suitable bond or letter of credit at least 30 days before its expiration date;
860.223. The letter of credit will be payable to the Division upon demand, in part or in full, upon receipt from the Division of a notice of forfeiture issued in accordance with R645-301-880.900.
860.230. Real property posted as a collateral bond will meet the following conditions:
860.231. The applicant will grant the Division a first mortgage, first deed of trust, or perfected first lien security interest in real property with a right to sell or otherwise dispose of the property in the event of forfeiture under state law;
860.232. In order for the Division to evaluate the adequacy of the real property offered to satisfy collateral requirements, the applicant will submit a schedule of the real property which will be mortgaged or pledged to secure the obligations under the indemnity agreement. The list will include:
860.232.1. A description of the property;
860.232.2. The fair market value as determined by an independent appraisal conducted by a certified appraiser approved by the Division; and
860.232.3. Proof of possession and title to the real property;
860.233. The property may include land which is part of the permit area; however, land pledged as collateral for a bond under this section will not be disturbed under any permit while it is serving as security under this section.
860.240. Cash accounts will be subject to the following conditions:
860.241. The Division may authorize the operator to supplement the bond through the establishment of a cash account in one or more federally insured or equivalently protected accounts made payable upon demand to, or deposited directly with, the Division. The total bond including the cash account will not be less than the amount required under terms of performance bonds including any adjustments, less amounts released in accordance with R645-301-880;
860.242. Any interest paid on a cash account will be retained in the account and applied to the bond value of the account unless the Division has approved the payment of interest to the operator;
860.243. Certificates of deposit may be substituted for a cash account with the approval of the Division; and
860.244. The Division will not accept an individual cash account in an amount in excess of $100,000 or the maximum insurable amount as determined by the Federal Deposit Insurance Corporation or the Federal Savings and Loan Insurance Corporation.
860.250. Bond Value of Collateral.
860.251. The estimated bond value of all collateral posted as assurance under this section will be subject to a margin which is the ratio of bond value to market values, as determined by the Division. The margin will reflect legal and liquidation fees, as well as value depreciation, marketability and fluctuations which might affect the net cash available to the Division to complete reclamation.
860.252. The bond value of collateral may be evaluated at any time, but it will be evaluated as part of the permit renewal and, if necessary, the performance bond amount increased or decreased. In no case will the bond value of collateral exceed the market value.
860.260. Persons with an interest in collateral posted as a bond, and who desire notification of actions pursuant to the bond, will request the notification in writing to the Division at the time collateral is offered.
860.300. Self-Bonding.
860.310. Definitions. Terms used in self-bonding are defined under R645-100-200.
860.320. The Division may accept a self bond from an applicant for a permit if all of the following conditions are met by the applicant or its parent corporation guarantor:
860.321. The applicant designates a suitable agent, resident within the state of Utah, to receive service of process;
860.322. The applicant has been in continuous operation as a business entity for a period of not less than five years. Continuous operation will mean that business was conducted over a period of five years immediately preceding the time of application:
860.322.1. The Division may allow a joint venture or syndicate with less than five years of continuous operation to qualify under this requirement if each member of the joint venture or syndicate has been in continuous operation for at least five years immediately preceding the time of application;
860.322.2. When calculating the period of continuous operation, the Division may exclude past periods of interruption to the operation of the business entity that were beyond the applicant's control and that do not affect the applicant's likelihood of remaining in business during the proposed coal mining and reclamation operations;
860.323. The applicant submits financial information in sufficient detail to show that the applicant meets one of the following criteria:
860.323.1. The applicant has a current rating for its most recent bond issuance of "A" or higher as issued by either Moody's Investor Service or Standard and Poor's Corporation;
860.323.2. The applicant has a tangible net worth of at least $10 million, a ratio of total liabilities to net worth of 2.5 times or less and a ratio of current assets to current liabilities of 1.2 times or greater; or
860.323.3. The applicant's fixed assets in the United States total at least $20 million and the applicant has a ratio of total liabilities to net worth of 2.5 times or less and a ratio of current assets to current liabilities of 1.2 times or greater; and
860.324. The applicant submits:
860.324.1. Financial statements for the most recently completed fiscal year accompanied by a report prepared by an independent certified public accountant in conformity with generally accepted accounting principles and containing the accountant's audit opinion or review opinion of the financial statements with no adverse opinion;
860.324.2. Unaudited financial statements for completed quarters in the current fiscal year;
860.324.3. Additional unaudited information as requested by the Division; and
860.324.4. Annual reports for the five years immediately preceding the time of application.
860.330. The Division may accept a written guarantee for an applicant's self bond from a parent corporation guarantor, if the guarantor meets the conditions of R645-301-860.321 through R645-301-860.324 as if it were the applicant. Such a written guarantee will be referred to as a "corporate guarantee." The terms of the corporate guarantee will provide for the following:
860.331. If the applicant fails to complete the reclamation plan, the guarantor will do so or the guarantor will be liable under the indemnity agreement to provide funds to the Division sufficient to complete the reclamation plan, but not to exceed the bond amount;
860.332. The corporate guarantee will remain in force unless the guarantor sends notice of cancellation by certified mail to the applicant and to the Division at least 90 days in advance of the cancellation date, and the Division accepts the cancellation; and
860.333. The cancellation may be accepted by the Division if the applicant obtains a suitable replacement bond before the cancellation date or if the lands for which the self bond, or portion thereof, was accepted have not been disturbed.
860.340. The Division may accept a written guarantee for an applicant's self bond from any corporate guarantor, whenever the applicant meets the conditions of R645-301-860.321, R645-301-860.322, and R645-301-860.324 and the guarantor meets the conditions of R645-301-860.321 through R645-301-860.324 as if it were the applicant. Such a written guarantee will be referred to as a "nonparent corporate guarantee." The terms of this guarantee will provide for compliance with the conditions of R645-301-860.331 through R645-301-860.333. The Division may require the applicant to submit any information specified in R645-301-860-323 in order to determine the financial capabilities of the applicant.
860.350. For the Division to accept an applicant's self bond, the total amount of the outstanding and proposed self bonds of the applicant for coal mining and reclamation operations will not exceed 25 percent of the applicant's tangible net worth in the United States. For the Division to accept a corporate guarantee, the total amount of the parent corporation guarantor's present and proposed self bonds and guaranteed self bonds for surface coal mining and reclamation operations will not exceed 25 percent of the guarantor's tangible net worth in the United States. For the Division to accept a nonparent corporate guarantee, the total amount of the nonparent corporate guarantor's present and proposed self bonds and guaranteed self bonds will not exceed 25 percent of the guarantor's tangible net worth in the United States.
860.360. If the Division accepts an applicant's self bond, an indemnity agreement will be submitted subject to the following requirements:
860.361. The indemnity agreement will be executed by all persons and parties who are to be bound by it, including the parent corporation guarantor, and will bind each jointly and severally;
860.362. Corporations applying for a self bond, and parent and nonparent corporations guaranteeing an applicant's self bond shall submit an indemnity agreement signed by two corporate officers who are authorized to bind their corporations. A copy of such authorization shall be provided to the Division along with an affidavit certifying that such an agreement is valid under all applicable federal and Utah laws. In addition, the guarantor shall provide a copy of the corporate authorization demonstrating that the corporation may guarantee the self bond and execute the indemnity agreement.
860.363. If the applicant is a partnership, joint venture or syndicate, the agreement will bind each partner or party who has a beneficial interest, directly or indirectly, in the applicant;
860.364. Pursuant to R645-301-880.900, the applicant, parent or nonparent corporate guarantor shall be required to complete the approved reclamation plan for the lands in default or to pay to the Division an amount necessary to complete the approved reclamation plan, not to exceed the bond amount.
860.365. The indemnity agreement when under forfeiture will operate as a judgment against those parties liable under the indemnity agreement.
860.370. The Division may require self-bonded applicants, parent and nonparent corporate guarantors to submit an update of the information required under R645-301-860.323 and R645-301-860-324 within 90 days after the close of each fiscal year following the issuance of the self bond or corporate guarantee.
860.380. If at any time during the period when a self bond is posted, the financial conditions of the applicant, parent, or nonparent corporate guarantor change so that the criteria of R645-301-860.323 and R645-301-860.340 are not satisfied, the permittee will notify the Division immediately and will within 90 days post an alternate form of bond in the same amount as the self bond. Should the permittee fail to post an adequate substitute bond, the provisions of R645-301-840.500 will apply.
870. Replacement of Bonds.
870.100. The Division may allow a permittee to replace existing bonds with other bonds that provide equivalent coverage.
870.200. The Division will not release existing performance bonds until the permittee has submitted, and the Division has approved, acceptable replacement performance bonds. Replacement of a performance bond pursuant to this section will not constitute a release of bond under R645-301-880.100 through R645-301-880.800.
880. Requirement to Release Performance Bonds.
880.100. Bond release application.
880.110. The permittee may file an application with the Division for the release of all or part of a performance bond. Applications may be filed only at times or during seasons authorized by the Division in order to properly evaluate the completed reclamation operations. The times or seasons appropriate for the evaluation of certain types of reclamation will be identified in the approved mining and reclamation plan.
880.120. Within 30 days after an application for bond release has been filed with the Division, the operator will submit a copy of an advertisement placed at least once a week for four successive weeks in a newspaper of general circulation in the locality of the coal mining and reclamation operations. The advertisement will be considered part of any bond release application and will contain the permittee's name, permit number and approval date, notification of the precise location of the land affected, the number of acres, the type and amount of the bond filed and the portion sought to be released, the type and appropriate dates of reclamation work performed, a description of the results achieved as they relate to the operator's approved reclamation plan and the name and address of the Division to which written comments, objections, or requests for public hearings and informal conferences on the specific bond release may be submitted pursuant to R645-301-880.600 and R645-301-880.800. In addition, as part of any bond release application, the applicant will submit copies of letters which he or she has sent to adjoining property owners, local governmental bodies, planning agencies, sewage and water treatment authorities, and water companies in the locality in which the coal mining and reclamation operation took place, notifying them of the intention to seek release from the bond.
880.130. The permittee shall include in the application for bond release a notarized statement which certifies that all applicable reclamation activities have been accomplished in accordance with the requirements of the Act, the regulatory program, and the approved reclamation plan. Such certification shall be submitted for each application or phase of bond release.
880.200. Inspection by the Division.
880.210. Upon receipt of the bond release application, the Division will, within 30 days, or as soon thereafter as weather conditions permit, conduct an inspection and evaluation of the reclamation work involved. The evaluation will consider, among other factors, the degree of difficulty to complete any remaining reclamation, whether pollution of surface and subsurface water is occurring, the probability of future occurrence of such pollution and the estimated cost of abating such pollution. The surface owner, agent or lessee will be given notice of such inspection and may participate with the Division in making the bond release inspection. The Division may arrange with the permittee to allow access to the permit area, upon request of any person with an interest in bond release, for the purpose of gathering information relevant to the proceeding.
880.220. Within 60 days from the filing of the bond release application, if no public hearing is held pursuant to R645-301-880.600, or, within 30 days after a public hearing has been held pursuant to R645-301-880.600, the Division will notify in writing the permittee, the surety or other persons with an interest in bond collateral who have requested notification under R645-301-860.260 and the persons who either filed objections in writing or objectors who were a party to the hearing proceedings, if any, if its decision to release or not to release all or part of the performance bond.
880.300. The Division may release all or part of the bond for the entire permit area if the Division is satisfied that all the reclamation or a phase of the reclamation covered by the bond or portion thereof has been accomplished in accordance with the following schedules for reclamation of Phases I, II and III:
880.310. At the completion of Phase I, after the operator completes the backfilling and regrading (which may include the replacement of topsoil) and drainage control of a bonded area in accordance with the approved reclamation plan, 60 percent of the bond or collateral for the applicable area;
880.320. At the completion of Phase II, after revegetation has been established on the regraded mined lands in accordance with the approved reclamation plan, an additional amount of bond. When determining the amount of bond to be released after successful revegetation has been established, the Division will retain that amount of bond for the revegetated area which would be sufficient to cover the cost of reestablishing revegetation if completed by a third party and for the period specified for operator responsibility in UCA 40-10-17(2)(t) of the Act for reestablishing revegetation. No part of the bond or deposit will be released under this paragraph so long as the lands to which the release would be applicable are contributing suspended solids to streamflow or runoff outside the permit area in excess of the requirements set by UCA 40-10-17(2)(j) of the Act and by R645-301-751 or until soil productivity for prime farmlands has returned to the equivalent levels of yield as nonmined land of the same soil type in the surrounding area under equivalent management practices as determined from the soil survey performed pursuant to UCA 40-10-11(4) of the Act and R645-301-200. Where a silt dam is to be retained as a permanent impoundment pursuant to R645-301-700, the Phase II portion of the bond may be released under this paragraph so long as provisions for sound future maintenance by the operator or the landowner have been made with the Division; and
880.330. At the completion of Phase III, after the operator has completed successfully all surface coal mining and reclamation operations, the release of the remaining portion of the bond, but not before the expiration of the period specified for operator responsibility in R645-301-357. However, no bond will be fully released under provisions of this section until reclamation requirements of the Act and the permit are fully met.
880.400. If the Division disapproves the application for release of the bond or portion thereof, the Division will notify the permittee, the surety, and any person with an interest in collateral as provided for in R645-301-860.260, in writing, stating the reasons for disapproval and recommending corrective actions necessary to secure the release and allowing an opportunity for a public hearing.
880.500. When an application for total or partial bond release is filed with the Division, the Division will notify the municipality in which the coal mining and reclamation activities are located by certified mail at least 30 days prior to the release of all or a portion of the bond.
880.600. Any person with a valid legal interest which might be adversely affected by release of the bond, or the responsible officer or head of any federal, state, or local governmental agency which has jurisdiction by law or special expertise with respect to any environmental, social or economic impact involved in the operation or which is authorized to develop and enforce environmental standards with respect to such operations, will have the right to file written objections to the proposed release from bond with the Division within 30 days after the last publication of the notice required by R645-301-880.120. If written objections are filed and a hearing is requested, the Division will inform all the interested parties of the time and place of the hearing and will hold a public hearing within 30 days after receipt of the request for the hearing. The date, time and location of the public hearing will be advertised by the Division in a newspaper of general circulation in the locality for two consecutive weeks. The public hearing will be held in the locality of the coal mining and reclamation operations from which bond release is sought, or at the location of the Division office, at the option of the objector.
880.700. For the purpose of the hearing under R645-301-880.600, the Division will have the authority to administer oaths, subpoena witnesses or written or printed material, compel the attendance of witnesses or the production of materials and take evidence including, but not limited to, inspection of the land affected and other surface coal mining operations carried on by the applicant in the general vicinity. A verbatim record of each public hearing will be made and a transcript will be made available on the motion of any party or by order of the Division.
880.800. Without prejudice to the right of an objector or the applicant, the Division may hold an informal conference as provided in UCA 40-10-13(2)(b) of the Act to resolve such written objections. The Division will make a record of the informal conference unless waived by all parties, which will be accessible to all parties. The Division will also furnish all parties of the informal conference with a written finding of the Division based on the informal conference and the reasons for said finding.
880.900. Forfeiture of Bonds.
880.910. If an operator refuses or is unable to conduct reclamation of an unabated violation, if the terms of the permit are not met, or if the operator defaults on the conditions under which the bond was accepted, the Division will take the following action to forfeit all or part of a bond or bonds for any permit area or an increment of a permit area:
880.911. Send written notification by certified mail, return receipt requested, to the permittee and the surety on the bond, if any, informing them of the determination to forfeit all or part of the bond including the reasons for the forfeiture and the amount to be forfeited. The amount will be based on the estimated total cost of achieving the reclamation plan requirements;
880.912. Advise the permittee and surety, if applicable, of the conditions under which forfeiture may be avoided. Such conditions may include, but are not limited to:
880.912.1. Agreement by the permittee or another party to perform reclamation operations in accordance with a compliance schedule which meets the conditions of the permit, the reclamation plan and the State Program and a demonstration that such party has the ability to satisfy the conditions; or
880.912.2. The Division may allow a surety to complete the reclamation plan, or the portion of the reclamation plan applicable to the bonded phase or increment, if the surety can demonstrate an ability to complete the reclamation in accordance with the approved reclamation plan. Except where the Division may approve partial release authorized under R645-301-880.100 through R645-301-880.800, no surety liability will be released until successful completion of all reclamation under the terms of the permit, including applicable liability periods of R645-301-820.300.
880.920. In the event forfeiture of the bond is required by this section, the Division will:
880.921. Proceed to collect the forfeited amount as provided by applicable laws for the collection of defaulted bonds or other debts if actions to avoid forfeiture have not been taken, or if rights of appeal, if any, have not been exercised within a time established by the Division, or if such appeal, if taken, is unsuccessful; and
880.922. Use funds collected from bond forfeiture to complete the reclamation plan, or portion thereof, on the permit area or increment, to which bond coverage applies.
880.930. Upon default, the Division may cause the forfeiture of any and all bonds deposited to complete reclamation for which the bonds were posted. Bond liability will extend to the entire permit area under conditions of forfeiture.
880.931. In the event the estimated amount forfeited is insufficient to pay for the full cost of reclamation, the operator will be liable for remaining costs. The Division may complete, or authorize completion of, reclamation of the bonded area and may recover from the operator all costs of reclamation in excess of the amount forfeited.
880.932. In the event the amount of performance bond forfeited was more than the amount necessary to complete reclamation, the unused funds will be returned by the Division to the party from whom they were collected.
890. Terms and Conditions for Liability Insurance.
890.100. The Division will require the applicant to submit as part of its permit application a certificate issued by an insurance company authorized to do business in Utah certifying that the applicant has a public liability insurance policy in force for the coal mining and reclamation activities for which the permit is sought. Such policy will provide for personal injury and property damage protection in an amount adequate to compensate any persons injured or property damaged as a result of the coal mining and reclamation operations, including the use of explosives and who are entitled to compensation under the applicable provisions of state law. Minimum insurance coverage for bodily injury and property damage will be $300,000 for each occurrence and $500,000 aggregate.
890.200. The policy will be maintained in full force during the life of the permit or any renewal thereof, including the liability period necessary to complete all reclamation operations under this chapter.
890.300. The policy will include a rider requiring that the insurer notify the Division whenever substantive changes are made in the policy including any termination or failure to renew.
890.400. The Division may accept from the applicant, in lieu of a certificate for a public liability insurance policy, satisfactory evidence from the applicant that it satisfies applicable state self-insurance requirements approved as part of the State Program and the requirements of R645-301-890.100 through R645-301-890.300.

Utah Admin. Code R645-301-800