Utah Admin. Code 33-112-501

Current through Bulletin 2025-01, January 1, 2025
Section R33-112-501 - Change Orders
(1) In addition to the requirements in Section 63G-6a-1207, for executive branch procurement units without independent procurement authority, the certifications required under Subsections 63G-6a-1207(1) and 63G-6a-1207(2) must be submitted in writing by the procurement unit to the procurement official before the commencement of any work to be performed under a contract change order unless:
(a) the procurement unit has authority Subsection 63G-6a-304(1) and Section R33-103-101 to authorize contract change orders up to the amount delegated; or
(b) the change order is:
(i) requisite to avert an emergency; or
(ii) required as an emergency.
(2) For purposes of Subsection (1)(b) "emergency" is described in Subsection R33-108-401(3) and is subject to Section 63G-6a-803.
(3) Any contract change order authorized by a procurement unit under Subsection R33-112-501(1)(c) shall, as soon as practicable, be submitted to the procurement official and included in the division's contract file.

Utah Admin. Code R33-112-501

Adopted by Utah State Bulletin Number 2024-15, effective 7/9/2024, exp. 11/6/2024 (Emergency)
Adopted by Utah State Bulletin Number 2024-21, effective 10/22/2024