Current through Reg. 49, No. 49; December 6, 2024
Section 3.15 - Surface Equipment Removal Requirements and Inactive Wells(a) Definitions. The following words and terms, when used in this section, shall have the following meanings, unless the context clearly indicates otherwise: (1) Active operation--Regular and continuing activities related to the production of oil and gas for which the operator has all necessary permits. In the case of a well that has been inactive for 12 consecutive months or longer and that is not permitted as a disposal or injection well, the well remains inactive for purposes of this section, regardless of any minimal activity, until the well has reported production of at least five barrels of oil for oil wells or 50 Mcf of gas for gas wells each month for at least three consecutive months, or until the well has reported production of at least one barrel of oil for oil wells or at least one Mcf of gas for gas wells each month for 12 consecutive months.(2) Cost calculation for plugging an inactive well--The cost, calculated by the Commission or its delegate, for each foot of well depth plugged based on average actual plugging costs for wells plugged by the Commission for the preceding state fiscal year for the Commission Oil and Gas Division district in which the inactive well is located.(3) Delinquent inactive well--An inactive well for which, after notice and opportunity for a hearing, the Commission or its delegate has not extended the plugging deadline.(4) Enhanced oil recovery (EOR) project--A project that does not include a water disposal project and is: (A) a Commission-approved EOR project that uses any process for the displacement of oil or other hydrocarbons from a reservoir other than primary recovery and includes the use of an immiscible, miscible, chemical, thermal, or biological process;(B) a certified project described by Texas Tax Code, § RSA 202.054; or(C) any other project approved by the Commission or its delegate for EOR.(5) Good faith claim--A factually supported claim based on a recognized legal theory to a continuing possessory right in a mineral estate, such as evidence of a currently valid oil and gas lease or a recorded deed conveying a fee interest in the mineral estate.(6) Inactive well--An unplugged well that has been spudded or has been equipped with cemented casing and that has had no reported production, disposal, injection, or other permitted activity for a period of greater than 12 months.(7) Operator designation form--A certificate of compliance and transportation authority or an application to drill, recomplete, and reenter that has been approved by the Commission or its delegate.(8) Physical termination of electric service to the well's production site--Disconnection of the electric service to an inactive well site at a point on the electric service lines most distant from the production site toward the main supply line in a manner that will not interfere with electrical supply to adjacent operations, including cathodic protection units.(b) Plugging of inactive bay and offshore wells required. (1) An operator of an existing inactive bay or offshore well as defined in § RSA 3.78 of this title (relating to Fees and Financial Security Requirements) must: (A) restore the well to active operation as defined by Commission rule;(B) plug the well in compliance with a Commission rule or order; or(C) obtain the approval of the Commission or its delegate of an extension of the deadline for plugging an inactive bay or offshore well.(2) The Commission or its delegate may not approve an extension of the deadline for plugging an inactive bay or offshore well if the plugging of the well is otherwise required by Commission rules or orders.(c) Extension of deadline for plugging an inactive bay or offshore well. The Commission or its delegate may administratively grant an extension of the deadline for plugging an inactive bay or offshore well as defined by Commission rules if: (1) the operator has a current organization report;(2) the operator has, and on request provides, evidence of a good faith claim to a continuing right to operate the well;(3) the well and associated facilities are otherwise in compliance with all Commission rules and orders; and(4) for a well more than 25 years old, the operator successfully conducts and the Commission or its delegate approves a fluid level or hydraulic pressure test establishing that the well does not pose a potential threat of harm to natural resources, including surface and subsurface water, oil, and gas.(d) Plugging of inactive land wells required. (1) An operator that assumes responsibility for the physical operation and control of an existing inactive land well must maintain the well and all associated facilities in compliance with all applicable Commission rules and orders and within six months after the date the Commission or its delegate approves an operator designation form must either: (A) restore the well to active operation as defined by Commission rule;(B) plug the well in compliance with a Commission rule or order; or(C) obtain approval of the Commission or its delegate of an extension of the deadline for plugging an inactive well.(2) The Commission or its delegate may not approve an extension of the deadline for plugging an inactive land well if the plugging of the well is otherwise required by Commission rules or orders.(3) Except for an operator designation form filed for the purpose of a name change, the Commission or its delegate may not approve an operator designation form for an inactive land well until the operator satisfies the requirements of paragraph (1)(C) of this subsection.(4) If an operator fails to restore the well to active operation as defined by Commission rule, plug the well in compliance with a Commission rule or order, or obtain an extension of the deadline for plugging an inactive well within six months after acquiring an inactive well, the Commission or its delegate may, after notice and opportunity for hearing, revoke the operator's organization report.(5) The Commission or its delegate may approve an organization report that is delinquent or has been revoked if the Commission or its delegate simultaneously approves extensions of the deadline for plugging the operator's inactive wells.(e) Extension of deadline for plugging an inactive land well. The Commission or its delegate may administratively grant an extension of the deadline for plugging an inactive land well if: (1) the Commission or its delegate approves the operator's Application for an Extension of Deadline for Plugging an Inactive Well (Commission Form W-3X);(2) the operator has a current organization report;(3) the operator has, and on request provides evidence of, a good faith claim to a continuing right to operate the well;(4) the well and associated facilities are otherwise in compliance with all Commission rules and orders; and(5) for a well more than 25 years old, the operator successfully conducts and the Commission or its delegate approves a fluid level or hydraulic pressure test establishing that the well does not pose a potential threat of harm to natural resources, including surface and subsurface water, oil, and gas.(f) Application for an extension of deadline for plugging an inactive land well. (1) This subsection does not apply to a bay well or an offshore well as those terms are defined in § RSA 3.78 of this title.(2) An operator must include the following in an application for an extension of the deadline for plugging an inactive well: (A) an affirmation made by an individual with personal knowledge of the physical condition of the inactive well pursuant to the provisions of Texas Natural Resources Code, § RSA 91.143, stating the following: that the operator has physically terminated electric service to the well's production site; and either: (i) if the operator does not own the surface of the land where the well is located and the well has been inactive for at least five years but for less than 10 years as of the date of renewal of the operator's organization report, that the operator has emptied or purged of production fluids all piping, tanks, vessels, and equipment associated with and exclusive to the well; or(ii) if the operator does not own the surface of the land where the well is located, and the well has been inactive for at least 10 years as of the date of renewal of the operator's organization report, that the operator has removed all surface equipment and related piping, tanks, tank batteries, pump jacks, headers, fences, and firewalls; has closed all open pits; and has removed all junk and trash, as defined by Commission rule, associated with and exclusive to the well; and(B) documentation that the operator has satisfied at least one of the following requirements: (i) for all inactive land wells that an operator has operated for more than 12 months, the operator has plugged or restored to active operation, as defined by Commission rule, 10% of the number of inactive land wells operated at the time of the last annual renewal of the operator's organization report;(ii) if the operator is a publicly traded entity, for all inactive land wells, the operator has filed with the Commission a copy of the operator's federal documents filed to comply with Financial Accounting Standards Board Statement No. 143, Accounting for Asset Retirement Obligations, and an original executed Uniform Commercial Code Form 1 Financing Statement, filed with the Secretary of State, that names the operator as the "debtor" and the Railroad Commission of Texas as the "secured creditor" and specifies the funds covered by the documents in the amount of the cost calculation for plugging all inactive wells;(iii) the filing of a blanket bond on Commission Form P-5PB(2), Blanket Performance Bond, a letter of credit on Commission Form P-5LC, Irrevocable Documentary Blanket Letter of Credit, or a cash deposit, in the amount of either the lesser of the cost calculation for plugging all inactive wells or $2 million;(iv) for each inactive land well identified in the application, the Commission has approved an abeyance of plugging report and the operator has paid the required filing fee;(v) for each inactive land well identified in the application, the operator has filed a statement that the well is part of a Commission-approved EOR project;(vi) for each inactive land well identified in the application that is not otherwise required by Commission rule or order to conduct a fluid level or hydraulic pressure test of the well, the operator has conducted a successful fluid level test or hydraulic pressure test of the well and the operator has paid the required filing fee;(vii) for each inactive land well identified in the application, the operator has filed Commission Form W-3X and the Commission or its delegate has approved a supplemental bond, letter of credit, or cash deposit in an amount at least equal to the cost calculation for plugging an inactive land well for each well specified in the application; or(viii) for each time an operator files an application for a plugging extension and for each inactive land well identified in the application, the operator has filed Commission Form W-3X and the Commission or its delegate has approved an escrow fund deposit in an amount at least equal to 10% of the total cost calculation for plugging an inactive land well.(g) Commission action on application for plugging extension. (1) The Commission or its delegate shall administratively grant all applications for plugging extensions that meet the requirements of Commission rules.(2) The Commission or its delegate may administratively deny an application for a plugging extension for an inactive well if the Commission or its delegate determines that: (A) the applicant does not have an active organization report at the time the plugging extension application is filed;(B) the applicant has not submitted all required filing fees and financial assurance for the requested plugging extension and for renewal of its organization report; or(C) the applicant has not submitted a signed organization report for the applied-for extension year that qualifies for approval regardless of whether the applicant has complied with the inactive well requirements of this section.(3) Except as provided in paragraph (2) of this subsection, if the Commission or its delegate determines that an organization report should be denied renewal solely because it does not meet the inactive well requirements of this section, a Commission delegate shall, within a reasonable time of not more than 14 days after receipt of the applicant's administratively complete organization report renewal packet, including all statutorily required fees and financial assurance: (A) notify the operator of the determination;(B) provide the operator with a written statement of the reasons for the determination; and(C) notify the operator that it has 90 days from the expiration of its most recently approved organization report to comply with the requirements of this section.(4) If, after the expiration of the 90-day period specified in paragraph (3)(C) of this subsection, the Commission or its delegate determines that the operator remains out of compliance with the requirements of this section, the Commission delegate shall mail the operator a written notice of this determination. The operator may request a hearing. If the operator fails to timely file a request for hearing and the required hearing fee, the Commission shall enter an order denying the plugging extension request and denying renewal of the operator's organization report without further notice or opportunity for hearing.(5) To request a hearing, the operator must file a written request for hearing and the hearing fee of $4,500 with the Hearings Division, no later than 30 days from the date the written notice was mailed to the operator. In the request for hearing, the operator must identify by its assigned American Petroleum Institute (API) number each inactive well for which the operator is seeking a hearing to contest the determination that the well remains out of compliance. At the time an operator files a request for hearing under this subsection, the operator shall provide a list of affected persons to be given notice of the hearing. Affected persons shall include the owners of the surface estate of each tract on which a well that is the subject of the hearing request is located, the director of the Commission's Enforcement Section, and the district director of each Commission district in which the wells are located. The applicant's failure to diligently prosecute a hearing requested under this subsection may result in the application being involuntarily dismissed for want of prosecution on the motion of any affected person or on the Commission's own motion.(6) If an operator files a timely plugging extension application that is not properly administratively denied for the reasons specified in paragraph (2) of this subsection, then the operator's previously approved organization report shall remain in effect until the Commission approves its plugging extension application or enters a final order denying the application.(h) Revocation of extension. The Commission or its delegate may revoke an extension of the deadline for plugging an inactive well if the Commission or its delegate determines, after notice and an opportunity for a hearing, that the applicant is ineligible for the extension under the Commission's rules or orders.(i) Removal of surface equipment for land wells inactive more than 10 years. Requirements to remove surface equipment for land wells inactive more than 10 years do not excuse an operator from compliance with all other applicable Commission rules and orders including the requirements in Chapter 4 of this title (relating to Environmental Protection). (1) An operator of an inactive land well must leave a clearly visible sign as required by § RSA 3.3 of this title (relating to Identification of Properties, Wells, and Tanks) at the wellhead of the well and must maintain wellhead control as required by § RSA 3.13 of this title (relating to Casing, Cementing, Drilling, and Completion Requirements).(2) An operator may not store surface equipment removed from an inactive land well on an active lease.(3) An operator may be eligible for a temporary extension of the deadline for plugging an inactive land well or a temporary exemption from the surface equipment removal requirements if the operator is unable to comply with the requirements of subsection (f)(2)(A) of this section because of safety concerns or required maintenance of the well site and the operator includes with the application a written affirmation of the facts regarding the safety concerns or maintenance.(4) An operator may be eligible for an extension of the deadline for plugging a well without complying with the surface equipment removal requirements for inactive land wells if the well is located on a unit or lease or in a field associated with an EOR project and the operator includes a statement in the written affirmation that the well is part of such a project. The exemption provided by this subsection applies only to the equipment associated with current and future operations of the project.(j) Abeyance of plugging report. (1) An operator that files an abeyance of plugging report must: (A) pay an annual fee of $100 for each inactive land well covered by the report;(B) use Commission Form W-3X on which the operator must specify the field and the covered wells within that field; and(C) for each well, include a certification signed and sealed by a person licensed by the Texas Board of Professional Engineers or the Texas Board of Professional Geoscientists stating that the well has: (i) a reasonable expectation of economic value in excess of the cost of plugging the well for the duration of the period covered by the report, based on the cost calculation for plugging an inactive well;(ii) a reasonable expectation of being restored to a beneficial use that will prevent waste of oil or gas resources that otherwise would not be produced if the well were plugged; and(iii) documentation demonstrating the basis for the affirmation of the well's future utility.(2) Except as provided in paragraph (3) of this subsection, the Commission or its delegate may not transfer an abeyance of plugging report to a new operator of an existing inactive land well. The new operator of an existing inactive land well must file a new abeyance of plugging report or otherwise comply with the requirements of this subchapter not later than six months after the date the Commission or its delegate approves the new operator's request to be recognized as the operator of the well.(3) The Commission or its delegate may transfer an abeyance of plugging report in the event of a change of name of an operator.(k) Enhanced oil recovery (EOR) project. (1) An inactive well is considered to be part of an EOR project if the well is located on a unit or lease or in a field associated with a Commission-approved EOR project.(2) Except as provided in paragraph (3) of this subsection, the Commission and its delegate may not transfer a statement that an inactive well is part of an EOR project to a new operator of an existing inactive well. A new operator of an existing inactive well must file a new statement stating that the well is part of such an EOR project or otherwise comply with the provisions of this section not later than six months after the date the Commission or its delegate approves the new operator's request to be recognized as the operator of the well.(3) The Commission or its delegate may transfer a statement that a well is part of an EOR project in the event of a change of name of an operator.(l) Fluid level or hydraulic pressure test for inactive wells more than 25 years old.(1) At least three days prior to the test, the operator must give the district office notice of the date and approximate time the operator intends to conduct a fluid level or hydraulic pressure test. The district office may require that a test be witnessed by a Commission employee. The district office may allow an operator to conduct a test even if notice of the test is provided to the district office fewer than three days prior to the test.(2) No operator may conduct a test other than a fluid level or hydraulic pressure test without prior approval from the district director or the director's delegate.(3) For each inactive well that is more than 25 years old and that has been inactive more than 10 years, the operator must perform either a fluid level test once every 12 months or a hydraulic pressure test once every five years and obtain the approval of the Commission or its delegate of the results of said tests.(4) Notwithstanding the provisions of paragraph (1) of this subsection, an operator may conduct a hydraulic pressure test without prior approval from the district director or the director's delegate, provided that the operator gives the district office written notice of the date and approximate time for the test at least three days prior to the time the test will be conducted; the production casing is tested to a depth of at least 250 feet below the base of usable quality water strata or 100 feet below the top of cement behind the production casing, whichever is deeper; and the minimum test pressure is greater than or equal to 250 psig for a period of at least 30 minutes.(5) Using Commission Form H-15, each operator must file in the Commission's Austin office the results of a successful fluid level test within 30 days of the date the test was performed. The results, if approved, are valid for a period of one year from the date of the test. Upon request by the Commission or its delegate, the operator must file the actual test data.(6) Using Commission Form H-5 or Form H-15, each operator must file in the district office the results of a successful hydraulic pressure test, including the original pressure recording chart or its electronic equivalent, within 30 days of the date the test was performed. The results, if approved, are valid for a period of five years from the date of the test, unless the Commission or its delegate requires the operator to perform testing more frequently to ensure that the well does not pose a threat of harm to natural resources.(7) An operator of an inactive well that is more than 25 years old may not return that inactive well to active operation unless the operator performs either a successful fluid level test of the well within 12 months prior to the return to activity or a successful hydraulic pressure test of the well within five years prior to the return to activity.(m) Fluid level or hydraulic pressure test for inactive land well less than 25 years old. (1) At least three days prior to the test, each operator must give the district office notice of the date and approximate time the operator intends to conduct a fluid level or hydraulic pressure test. The district office may require that a test be witnessed by a Commission employee. The district office may allow an operator to conduct a test even if notice of the test is provided to the district office fewer than three days prior to the test.(2) No operator may conduct a test other than a fluid level or hydraulic pressure test without prior approval from the district director or the director's delegate.(3) Notwithstanding the provisions of paragraph (1) of this subsection, an operator may conduct a hydraulic pressure test without prior approval from the district director or the director's delegate, provided that the operator gives the district office written notice of the date and approximate time for the test at least three days prior to the time the test will be conducted; the production casing is tested to a depth of at least 250 feet below the base of usable quality water strata or 100 feet below the top of cement behind the production casing, whichever is deeper; and the minimum test pressure is greater than or equal to 250 psig for a period of at least 30 minutes.(4) An operator that files documentation of a fluid level test or a hydraulic pressure test for an inactive land well less than 25 years old in order to obtain a plugging extension must pay an annual fee of $50 for each well covered by the documentation.(5) Using Commission Form H-15, each operator must file in the Commission's Austin office the results of a successful fluid level test within 30 days of the date the test was performed. The results, if approved, are valid for a period of one year from the date of the test. Upon request by the Commission or its delegate, the operator must file the actual test data.(6) Using Commission Form H-5 or Form H-15, each operator must file in the district office the results of a successful hydraulic pressure test, including the original pressure recording chart or its electronic equivalent, within 30 days of the date the test was performed. The results, if approved, are valid for a period of five years from the date of the test, unless the Commission or its delegate requires the operator to perform testing more frequently to ensure that the well does not pose a threat of harm to natural resources.(7) The Commission or its delegate may transfer documentation of the results of a fluid level or hydraulic pressure test to a new operator of an existing inactive land well that is less than 25 years old.(n) Supplemental financial assurance. (1) A supplemental bond, letter of credit, or cash deposit filed as part of an application for an extension for an inactive land well is in addition to any other financial assurance otherwise required of the operator or for the well.(2) The Commission or its delegate may not transfer a supplemental bond, letter of credit, or cash deposit to a new operator of an existing inactive land well. A new operator of an existing inactive land well must file a new supplemental bond, letter of credit, or cash deposit or otherwise comply with the provisions of this section not later than six months after the date the Commission or its delegate approves an operator designation form.(o) Escrow funds. (1) An operator must deposit escrow funds with the Commission each time the operator files an application for an extension of the deadline for plugging an inactive well.(2) The Commission or its delegate may release escrow funds deposited with the Commission only as prescribed by § RSA 3.78 of this title.(p) Plugging more than 10% of inactive well inventory. If an operator plugs more than 10% of the number of inactive land wells during a 12-month organization report cycle, the Commission will count the number of plugged wells above 10% toward fulfillment of the 10% blanket option under subsection (f)(2)(B)(i) of this section during the next organization report cycle.16 Tex. Admin. Code § 3.15
The provisions of this §3.15 adopted to be effective September 13, 2010, 35 TexReg 8332; amended to be effective August 15, 2011, 36 TexReg 5096; amended to be effective July 2, 2012, 37 TexReg 4894; Amended by Texas Register, Volume 41, Number 49, December 2, 2016, TexReg 9465, eff. 1/1/2017