Tenn. Comp. R. & Regs. 1200-03-25-.03

Current through December 26, 2024
Section 1200-03-25-.03 - EXISTING SOURCE COMPLIANCE SCHEDULES
(1) Incinerators in existence before November 6, 1988 must be in compliance, on or before 18 month from November 6, 1988, with the standards and requirements of this chapter. Each owner or operator of an existing incinerator shall either demonstrate compliance with the requirements of this chapter or submit a compliance schedule detailing the plan of action to achieve compliance within the above 18-month time frame to the Technical Secretary within 180 days from November 6, 1988.
(2) Individual compliance schedules for existing incinerators approved under this rule must contain the following increments of progress and achieve final compliance with the specified emission standards and requirements.
(a) Date contract will be awarded
(b) Date initial construction will commence
(c) Date construction will be completed
(d) Date final compliance will be achieved
(e) Date of compliance demonstration
(3) The individual compliance schedule must be received and approved by the Technical Secretary prior to the date of the first increment of progress.

Tenn. Comp. R. & Regs. 1200-03-25-.03

Original rule filed September 21, 1988; effective November 6, 1988.

Authority: T.C.A. §§ 68-25-105 and 4-5-202.