The secretary may issue a general permit to a category of air pollution sources that meets the following:
If a general permit has been issued by the secretary, all sources covered by the general permit shall apply for permission to operate under the general permit. Such sources may not be constructed or operate until they are granted coverage under the general permit, or until they obtain an individual permit if required by the secretary.
S.D. Admin. R. 74:36:04:32
General Authority: SDCL 34A-1-21.
Law Implemented: SDCL 34A-1-56.
Note: The procedural requirements for obtaining a general permit under this chapter are similar to the procedural requirements for a minor source, such as a timely and complete application, completeness review, public participation, and departmental recommendation, as outlined in §§ 74:36:04:06 to 74:36:04:14, inclusive.