The notification, work practice, clean-up, and disposal requirements of this Section shall apply to each abatement project where the combined amount of RACM to be stripped, removed, dislodged, cut, drilled, or similarly disturbed is equal to or fewer than 25 linear feet on pipes, or is equal to or fewer than 25 square feet on other facility components, or is equal to or fewer than 10 cubic feet of RACM off facility components where the area or the length or area could not be measured prior to abatement.
In a facility being abated subject to this Section:
The facility owner shall ensure that air sampling is performed in accordance with applicable requirements of the Air Sampling Section of this regulation.
The owner/operator shall comply with the requirements of the Disposal Section of this regulation.