No electrical utility supplying electric service to the public shall hereafter begin the construction or operation of any electric facilities, or of any extension thereof, without first obtaining from the commission a certificate that public convenience and necessity requires or will require such construction or operation; such certificate to be granted only after notice to the ORS, other interested electric systems and to the public, and after due hearing; provided, however, that this regulation shall not be construed to require any such electrical utility to secure a certificate for any extension within a municipality or district within which it has heretofore lawfully commenced operations, or for an extension within or to territory already served by it, necessary in the ordinary course of its business, or for an extension into territory contiguous to that already occupied by it and not receiving similar service from another electrical utility, but if any electric system in constructing or extending its lines, plant or system unreasonably interferes, or is about to unreasonably interfere, with the service or the system of any other electric system, the commission may make such order and prescribe such terms and conditions in harmony with this regulation as are just and reasonable.
1. Rural Territorial Act. The commission has assigned all areas outside municipal limits, and more than 300 feet from the lines (as defined in Section 58-27-610(3) of the South Carolina Code of Laws), as such lines existed on the dates of assignments, of any electric supplier (except some territory which was left unassigned to any supplier), and no electric supplier shall construct lines and equipment except as provided by S.C. Code of Laws, Sections 58-27-620(2); 58-27-620(4); 58-27-620(6); 58-27-650; and 58-27-660(1), into territory assigned to another supplier without prior approval of the commission; and no electric supplier shall construct permanent lines and equipment into any territory left unassigned by the commission pursuant to S.C. Code Ann., Section 58-27-640 without prior notice to the commission and the ORS filed within a reasonable period of time prior to the date of actual construction of permanent lines, which notice shall include a map of the area showing existing facilities, location of the customer, and the proposed route of the permanent line, and a written certification that those electric suppliers furnishing electric service in any areas contiguous to the unassigned territory have been provided a copy of the notice of construction of facilities as filed with the commission and provided to the ORS, and all such facilities providing electric service shall be constructed in accordance with good utility practices and all other applicable provisions of the S.C. Code of Laws, as amended.2. Utility Facility Siting and Environmental Protection Act. No electric system subject to the jurisdiction of the commission shall begin the construction and/or operation of any transmission line with a designed voltage of 125 KV or more or the construction and/or operation of a generating station of more than 75 megawatts, except a hydroelectric generating facility, before receiving a certificate of Environmental Compatibility and Public Convenience and Necessity in accordance with Sections 58-33-10 et seq., of the Code of Laws of South Carolina, 1976.S.C. Code Regs. § 103-304
Amended by State Register Volume 14, Issue No. 3, eff March 23, 1990; State Register Volume 32, Issue No. 5, eff May 23, 2008.