Current through Register Vol. 54, No. 45, November 9, 2024
Section 54.187 - Default service rate design and the recovery of reasonable costs(a) The Commission may modify contracts or disallow costs when after a hearing the party seeking recovery of the costs of a procurement plan is found to be at fault for either of the following: (1) Not complying with the Commission-approved procurement plan.(2) The commission of fraud, collusion or market manipulation with regard to these contracts.(b) The costs incurred for providing default service shall be recovered on a full and current basis through a reconcilable automatic adjustment clause under 66 Pa.C.S. § 1307 (relating to sliding scale of rates; adjustments), all reasonable costs incurred under 66 Pa.C.S. § 2807(e)(3.9) (relating to duties of electric distribution companies) and a Commission-approved competitive procurement plan. The use of an automatic adjustment clause shall be subject to audit and annual review, consistent with 66 Pa.C.S. § 1307(d) and (e).(c) Except for rates available consistent with § 54.190 (relating to universal interest applicable to over collections and under collections resulting from reconciliation of automatic adjustment clauses costs and revenues related to electric default service), a default service customer shall be offered a single rate option, which shall be identified as the PTC and displayed as a separate line item on a customer's monthly bill.(d) The rates charged for default service may not decline with the increase in kilowatt hours of electricity used by a default service customer in a billing period.(e) The PTC shall be designed to recover all default service costs, including generation, transmission and other default service cost elements, incurred in serving the average member of a customer class. An EDC's default service costs may not be recovered through the distribution rate. Costs currently recovered through the distribution rate, which are reallocated to the default service rate, may not be recovered through the distribution rate. The distribution rate shall be reduced to reflect costs reallocated to the default service rate.(f) A DSP shall use an automatic energy adjustment clause, consistent with 66 Pa.C.S. § 1307 and Chapter 75 (relating to alternative energy portfolio standards), to recover all reasonable costs incurred through compliance with the Alternative Energy Portfolio Standards Act (73 P. S. § § 1648.1-1648.8). The use of an automatic adjustment clause shall be subject to audit and annual review, consistent with 66 Pa.C.S. § 1307(d) and (e), regarding fuel cost adjustment audits and automatic adjustment reports and proceedings.(g) The default service rate schedule must include rates that correspond to demand side response and demand side management programs, as defined in section 2 of the Alternative Energy Portfolio Standards Act (73 P. S. § 1648.2), when the Commission mandates these rates pursuant to its authority under 66 Pa.C.S. Chapter 1 (relating to general provisions).(h) Default service rates may not be adjusted more frequently than on a quarterly basis for all customer classes with a maximum registered peak load up to 25 kW, to ensure the recovery of costs reasonably incurred in acquiring electricity at the least cost to customers over time. DSPs may propose alternative divisions of customers by maximum registered peak load to preserve existing customer classes.(i) Default service rates shall be adjusted on a quarterly basis, or more frequently, for all customer classes with a maximum registered peak load of 25 kW to 500 kW, to ensure the recovery of costs reasonably incurred in acquiring electricity at the least cost to customers over time. DSPs may propose alternative divisions of customers by maximum registered peak load to preserve existing customer classes.(j) Default service rates shall be adjusted on a monthly basis, or more frequently, for all customer classes with a registered peak load of equal to or greater than 500 kW to ensure the recovery of costs reasonably incurred in acquiring electricity at the least cost to customers over time. DSPs may propose alternative divisions of customers by registered peak load to preserve existing customer classes.(k) When a supplier fails to deliver electric generation supply to a DSP, the DSP shall be responsible for acquiring replacement electric generation supply consistent with its Commission-approved contingency plan. When necessary to procure electric generation supply before the implementation of a contingency plan, a DSP shall acquire supply at the least cost to customers over time and fully recover all reasonable costs associated with this activity that are not otherwise recovered through its contract terms with the default supplier. The DSP shall follow acquisition strategies that reflect the incurrence of reasonable costs, consistent with 66 Pa.C.S. § 2807, when selecting from the various options available in these energy markets.The provisions of this §54.187 amended August 10, 2012, effective 8/11/2012, 42 Pa.B. 5185; amended December 18, 2015, effective 12/19/2015, 45 Pa.B. 7161. This section cited in 52 Pa. Code § 54.188 (relating to commission review of default service programs and rates); 52 Pa. Code § 54.190 (relating to universal interest applicable to over collections and under collections resulting from reconciliation of automatic adjustment clauses costs and revenues related to electric default service); and 52 Pa. Code § 75.67 (relating to alternative energy cost-recovery).