Section 89.11 - General requirements

As required by Chapter 102 (relating to erosion and sediment control), the operator shall prepare and submit, as part of the application, an erosion and sedimentation control plan for all areas disturbed by earthmoving activities. The erosion and sedimentation control plan shall include, at a minimum, the information required by this subchapter, and shall be designed and implemented to achieve the performance standards set forth in this subchapter.

25 Pa. Code § 89.11

The provisions of this §89.11 adopted December 19, 1980, 10 Pa.B. 4789, effective 7/31/1982, 12 Pa.B. 2382; amended July 30, 1982, 12 Pa.B. 2473, effective 7/31/1982, 12 Pa.B. 2382.

This section cited in 25 Pa. Code § 88.493 (relating to minimum environmental protection performance standards).