Section 83.361 - Initial plan review and approval
(a) Plans for NMP operations shall be submitted for initial review and approval to delegated conservation districts, or alternatively to the Commission for NMP operations located in counties not delegated administrative authority under § 83.241 (relating to delegation to local agencies). A person performing the plan review shall be certified in accordance with the Department of Agriculture's nutrient management specialist certification requirements in 7 Pa. Code §§130b.1-130b.51 (relating to nutrient management certification).
(b) The Commission or a delegated conservation district will, within 10 days from the date of receipt of the plan, provide notice to the operator indicating whether all of the required plan elements have been received.
(c) The Commission or a delegated conservation district will approve or disapprove the plan or plan amendment within 90 days of receipt of a complete plan or plan amendment.
(d) If the Commission or delegated conservation district does not act on the plan within the 90-day period, the agricultural operation that submitted the plan is authorized to implement the plan. The Commission or delegated conservation district will thereafter have another 90 days to complete review of the plan, beginning on the expiration of the initial 90-day review period. If the Commission or delegated conservation district fails to act within the second 90-day period, it will be deemed approved.
(e) The notice of determination to disapprove a plan will be provided in writing to the operator submitting the plan, and include an explanation specifically stating the reasons for disapproval. If a plan for a CAO is disapproved, the operator submitting the plan for the first time shall have 90 days after receipt of the notice of disapproval to resubmit a revised plan.
(f) Approvals will be granted only for those plans that satisfy the requirements of this subchapter, including verification by the delegated conservation district or the Department of Environmental Protection that the operation has a current agricultural erosion and sediment control plan. For CAOs and VAOs existing on October 1, 2006, this agricultural erosion and sediment control plan verification is not required until October 1, 2009.