Current through Register Vol. 54, No. 49, December 7, 2024
Section 77.125 - Review of permit applications(a) The Department will review the complete application, written comments, written objections and records of a public hearing or informal conference.(b) If the Department decides to approve the application, it will require that the applicant file the performance bond under Subchapter D (relating to bonding and insurance requirements) before the permit is issued.The provisions of this § 77.125 adopted March 16, 1990, effective 3/17/1990, 20 Pa.B. 1643.