Or. Admin. Code § 734-051-8025

Current through Register Vol. 63, No. 12, December 1, 2024
Section 734-051-8025 - Access Management Dispute Review Board Process
(1) The actions and recommendations of the Access Management Dispute Review Board are not land use decisions, as defined in ORS 197.015, and may not be appealed to the Land Use Board of Appeals.
(2) Where more than one affected real property owner with the same or similar concerns requests review by an Access Management Dispute Review Board of the Key Principles and related Methodology for a facility plan or an Access Management Methodology for a highway project, the Department may consolidate the reviews.
(3) The Access Management Dispute Review Board shall include the following:
(a) The Director, or a designee of the Director, who is familiar with the location in which the facility plan is being prepared;
(b) A representative of the local jurisdiction for which the state highway is located;
(c) A traffic engineer who practices engineering in Oregon; and
(d) A representative from the economic or business sector.
(4) The Access Management Dispute Review Board shall be conducted not later than forty-five (45) calendar days from the date of written request from the affected real property owner(s), unless the Department and affected real property owner(s) agree to an time extension in writing. The Access Management Dispute Review Board shall make its recommendation to the Director not later than fourteen (14) calendar days following the conclusion of its deliberations.

Or. Admin. Code § 734-051-8025

HWD 7-2013(Temp), f. 12-23-13, cert. ef. 1-1-14 thru 6-30-14; Temporary suspended by HWD 2-2014, f. 6-25-14, cert. ef. 6-30-14; Temporary suspended by HWD 7-2014, f. & cert. ef. 7-9-14

Stat. Auth.: ORS 374.310-374.314, 374.345, 374.355, 374.360

Stats. Implemented: ORS 374.300 to 374.360, §27, ch. 330, OL 2011, ch. 476, OL 2013