Or. Admin. Code § 350-082-0120

Current through Register Vol. 63, No. 12, December 1, 2024
Section 350-082-0120 - Comment Periods
(1) Comments on Proposed Review Uses or Development. Interested persons have 21 days from the date the Executive Director sends the notice to submit written comments to the Executive Director relative to the consistency of the proposed actions with the guidelines of Commission Rule 350-082.
(a) Tribal governments shall have 30 days from the date the Executive Director sends the notice to submit written comments on the proposed action, and in their comments may request that the Executive Director consult with the tribal government regarding potential effects or modifications to treaty or other rights of the tribe.
(b) Where another provision of this land use ordinance specifies a longer time for specific agencies to review and comment on an application, that longer time shall apply to those agencies.
(2) Comments on Expedited Development and Uses. Interested persons have ten days from the date the Executive Director sends the notice to submit written comments to the Executive Director relative to the consistency of the proposed actions with the guidelines of 350-082-0220.
(3) Comments on Cultural Resource Surveys. Upon receipt of a completed cultural resources survey, the Executive Director shall forward the survey to the applicable State Historic Preservation Officer, and the four tribal governments. The State Historic Preservation Officer and the four tribal governments shall have 30 days to submit comments on the cultural resources survey. This comment period for cultural resource surveys may or may not run concurrently with the comment period in section (1) or (2) above.

Or. Admin. Code § 350-082-0120

CRGC 1-2022, adopt filed 03/02/2022, effective 5/1/2022

Statutory/Other Authority: ORS 196.150, RCW 43.97.015, 16 USC § 544e(c), 16 USC § 544f(l)

Statutes/Other Implemented: ORS 196.150, RCW 43.97.015, 16 USC § 544e(c), 16 USC § 544f(l)