Current through Register Vol. 63, No. 12, December 1, 2024
Section 345-027-0030 - Amendment to Extend Construction Beginning and Completion Deadlines(1) The certificate holder may request an amendment to extend the deadlines for beginning or completing construction of the facility that the Council has specified in a site certificate or an amended site certificate. The certificate holder shall submit a request that includes an explanation of the need for an extension and that conforms to the requirements of 345-027-0060 no later than six months before the date of the applicable deadline, or, if the certificate holder demonstrates good cause for the delay in submitting the request, no later than the applicable deadline.(2) A request within the time allowed in section (1) to extend the deadlines for beginning or completing construction suspends those deadlines until the Council acts on the request.(3) The Council shall review the request for amendment as described in OAR 345-027-0070.(4) If the Council grants an amendment under this rule, the Council shall specify new deadlines for beginning or completing construction that are not more than two years from the deadlines in effect before the Council grants the amendment.(5) To grant an amendment extending the deadline for beginning or completing construction of an energy facility subject to OAR 345 024 0550, 345 024 0590, or 345 024 0620, the Council must find that the facility complies with the carbon dioxide standard in effect at the time of the Council's order on the amendment.Or. Admin. Code § 345-027-0030
EFSC 1-1993, f. & cert. ef. 1-15-93; EFSC 5-1994, f. & cert. ef. 11-30-94; EFSC 2-1999, f. & cert. ef. 4-14-99; EFSC 1-2007, f. & cert. ef. 5-15-07; EFSC 1-2012, f. & cert. ef. 5-15-12Stat. Auth.: ORS 469.470
Stats. Implemented: ORS 469.370, 469.405 & 469.503